PROPOSED LISTER HILL NATIONAL CENTER for BIOMEDICAL COMMUNICATIONS and other facilities NATIONAL LIBRARY OF MEDICINE FEASIBILITY STUDY O'CONNOR & KILHAM ARCHITECTS 101 PARK AVENUE NEW YORK N. Y. 1969 NATIONAL LIBRARY OF MEDICINE WITH PROPOSED LHNCBC BUILDING O'CONNOR & KILHAM ARCHITECTS 1969 PROPOSED LISTER HILL NATIONAL CENTER for BIOMEDICAL COMMUNICATIONS and other facilities NATIONAL LIBRARY OF MEDICINE FEASIBILITY STUDY O'CONNOR & KILHAM ARCHITECTS 101 PARK AVENUE NEW YORK N. Y. 1969 I CONTENTS Page No, 3, Linkage 10 4. Relationships 10 5* Future Projects 10 6, Flexibility 10 7, Fogarty Center 10 8, Parking 10 9, Fallout Protection 10 10, Utilities 10 III. SURVEY A. Requirements 1, Feasibility Study 11 2, Scope 11 3, Delivery 11 B. Activities of NLM 1* Activities 13 2, Organization 13 3, Departmental Activities 13 4, Growth of Activities - 5 year plan 15 5, Photographs 16 C. Present Conditions 1, Project Location 16 2, Project Site Plan of N.L.M, 16 3, Facilities off N.IaH, Site 19 4, Lunch Room Facility* "A" Level 19 List of Illustrations Page No, 1 • SYNOPSIS A, Summary 1 1, Feasibility Study I - NLM 1 2, Feasibility Study II - NMAC 1 3, Feasibility Study III - LHNCBC/NMAC 2 4, Revision of Program 2 5, Conclusions 2 B, Preface 5 H, GENERAL A, Authorization 6 B, Character & Extent of Services 6 C, Background Information 1. NLM 7 2. NMAC 7 D, The Need 8 E, Information Furnished 1. By NLM 8 2, Information Available to Architects 9 F, Meetings 9 G, Criteria 1, Existing NLM Bldg. 10 2, New Structure 10 II Page No. Page No. C. Schematic Plans & Relationships 1. Linkage 54 2. New Building 58 3. Rehabilitation of NLM 59 D. Approach to Design of New Structure 1. Location on Site 59 2. General Shape & Design Characteristics 60 3. Future Expansion 60 V. CONSTRUCTION & COST A. Outline Specifications 1. Site Development 60 2. Utilities 60 3. Rehabilitation of Existing NLM Building 61 4. General Construction of New Building 61 B. Cost Estimates 1. New Building 63 2, Existing Building - Rehabilitation 63 3. Summary 63 4, General Notes 63 C. Schedule 63 APPENDIX I 1-1 to 1-22 1974 NLM Expansion Program in Bethesda Pro- posed New LHNCBC Building and Rehabilita- tion of Existing NLM Building APPENDIX II II-l to I1-6 1974 NMAC Program - NLM Needs in Atlanta APPENDIX III III-l Information Furnished to Architects 5. Utilities 19 6. Foundation Conditions 19 7. Zoning, Codes & Controls 19 8. Existing Plan of NLM 19 D. Five Year Expansion 1. Projected Expansion of Personnel & Space Requirements 25 2. Types of Space Required 26 3. Departmental Space Allocations 26 4. Special Considerations 30 iv, development A. Program as of 1974 - Bethesda 1. Schedules 37 2. Diagrammatic Plans 37 3. NMAC - Atlanta 37 4. Graphic Comparisons 50 B. Specific Areas and Details 1. Growth of Bookstacks 50 2. Growth of Microfilm Storage 51 3. Graphic Image Storage & Retrieval System 51 4. Development of Biomedical Communications Network 53 5. Communications Laboratory Facilities 54 6. Audiovisual Equipment & Use 54 7. Audiovisual Production Facilities. NMAC 54 iii LIST OF ILLUSTRATIONS Exhibits Page No. 1 Bar Chart 3 1A Summary Sketches 4 2 Organization Chart 1969 12 3 Site Plan of NIH 1969 17 4 NLM Site Plan 18 5 1969 Mezzanine Floor Plan 20 6 1969 First Floor Plan 21 7 1969 "A" Level Plan 22 8 1969 lfB" Level Plan 23 9 1969 "C" Level Plan 24 10 Organizational Relationship Diagram 27 11 Physical Relationship Diagram 28 12 Proposed NLM Program for 1974 (Bethesda) 29 13 Literature Collection 31 14 1974 Program Summary of Personnel and Areas 38 14A 1974 Program Summary of Personnel & Areas (contd) 39 15 1969 Mezzanine - Diagrammatic Plan 40 15A 1974 Mezzanine - Diagrammatic Plan 41 16 1969 First Floor - Diagrammatic Plan 42 16A 1974 First Floor - Diagrammatic Plan 43 17 1969 "A" Level Diagrammatic Plan 44 17A 1974 "A" Level Diagrammatic Plan 45 18 1969 ,fB" Level Diagrammatic Plan 46 18A 1974 "B" Level Diagrammatic Plan 47 19 1969 "C" Level Diagrammatic Plan 48 19A 1974 MC" Level Diagrammatic Plan 49 20 NMAC Alternates 50 21 Compact Storage 52 22 LHNCBC - Site Plan - Terrace Level 55 23 LHNCBC - "A" Level (Link) 56 24 LHNCBC - ftBM & "C" Levels, Section 57 25 Design and Construction Progress Schedule 64 Photographs and Renderings Page No. Rendering of NLM with proposed LHNCBC Front Photographs 1 through 9 32 Photographs 10 through 18 33 Photographs 19 through 27 34 Photographs 28 through 36 35 Photographs of Scale Model Back Photo Credits; Photographs Nos. 12, 13, 14, 15 on page 33, Courtesy of the National Medical Audiovisual Center. Photograph No. 24 on page 34, Courtesy of the NLM• 1 FEASIBILITY STUDY III PROPOSED LISTER HILL NATIONAL CENTER for BIOMEDICAL COMMUNICATIONS AND OTHER FACILITIES for the NATIONAL LIBRARY OF MEDICINE I. SYNOPSIS A, Summary 1• Feasibility Study I, NLM, The initial Feasibility Study (1967) (Blue Book) called for the study of requirements for construction of Additional Facilities for the expanding activities of the National Library of Medicine, The purpose was to accommodate "the total space require- ments of the present and planned programs of the NLM in the most efficient manner and making maximum utilization of the present NLM building," The project would have increased the facilities of the NLM by 230,000 sq,ft, to a total of 462,000 sq,ft. gross at a total cost of approximately $10,500,000 as of June 1967, including parking facilities and rehabilitation of the existing National Library of Medicine building to traditional library purposes, 2, Fusibility Study II, NMAC, Following the designation of the National Medical Audiovisual Center in Atlanta as a component part of the NLM (1 July 1967) a second Feasibility Study (1968) (Grey Book) investigated the alternatives of expansion of the NMAC in Atlanta or its relocation in new con- struction on the site of the NLM at Bethesda, The investigation in Atlanta was limited to an expansion of the existing NMAC building. This new construction was, of necessity, over existing parking spaces of the 2 CDC, The CDC itself already had future plans for the maximum utilization of its restricted site for its own purpose as well as the small amount of adjacent land that might become available. It was not considered advisable at the time of this survey to investigate a new site with a new building for the NMAC, The NMAC currently occupies 43,800 sq.ft, in the NCDC building outside Atlanta, The 9,100 sq.ft, gross additional has now been given up for 14,000 sq.ft, of rented space nearby. The conclusions and recommendations of this second report were that the NMAC might preferably be relocated in Bethesda with a total of 153,600 sq.ft, gross at an approximate cost of $5,900,000, The second study further recommended that the NMAC project be combined with the initial expansion project of the NLM into one integrated structure connected to the existing NLM building in order to realize the economies resulting from consolidation of administrative and other common purpose space. Budget forecasts and program plans used as the basis for these studies were somewhat optimistic in the light of FY-68/69 restrictions on personnel and fiscal obligations and program growth. In addition some of the non-program facilities, such as cafeteria and parking space, included in the proposed buildings will be incorporated in the program of requirements for the Fogarty International Center, a building to be con- structed adjacent to the NLM. For these reasons, and in the interest of federal economy, the NLM decided to examine the feasibility of combining the requirements of both studies in one building, each with reduced program to meet the new economic situation, 3. Feasibility Study III, LHNCBC/NMAC, In August 1968, by passage of Public Law 90-456, the proposed additional facilities for the NLM in Study I were designated the Lister Hill National Center for Biomedical Communications (LHNCBC), Since then, restrictions on obligations and programs have reduced the building program to a total of 218,000 sq.ft, of new construction at a cost estimated as of June 1969 of $11,121,000, Initially this third Feasibility Study-1969 (Red Book) was to update the requirements contained in Studies I and II, and explore the combination of the initial LHNCBC project with the NMAC project for location in one building at Bethesda as compared to one for the LHNCBC alone, omitting the NMAC, Early in the study it became clear the program for the LHNCBC and all other programs for space in the new building would have to be substantially reduced if the NMAC was to be accommodated in this same structure. Of the possible total of 230,000 sq.ft, gross (149,000 sq.ft, net useable space) only 131,000 sq.ft, would have been available to the new and expanded program of the NLM - the difference being taken care of as now, by rental space, or by assigned space in other buildings. Many program space requirements would have been subject to deferment, all as indicated in Bar Chart Exhibit 1, (Facing Page) The NMAC program would have been similarly handicapped by requiring supplemental rental space, 4. Revision of Program In view of these handicaps the NLM decided the NMAC would probably have to remain in Atlanta, Without the NMAC the NLM could have all its basic needs met in accordance with the revised program for the LHNCBC, This report has now been modified to determine what the space requirements of the LHNCBC without the NMAC would be up to 1974, and what the estimated costs would be as of June 1969, with projections, so that planning can proceed on schedule if funds are authorized, A revised program for the NMAC for its independent expansion in Atlanta is included in the Appendix, The exclusion of the NMAC from the LHNCBC building creates a need that must be met in future years. This third study has determined NMAC space requirements through 1974 - existing facilities are insufficient to meet these requirements. In addition CDC has pressing growth needs that must be accommodated on the CDC site. If NMAC projected requirements outlined in the study are to be satisfied their independent expansion at a separate site in Atlanta must be investigated, 5, Conclusions a. Estimates & Projections 1) Personnel - Assumed projection from 517 in 1969 to 1039 in 1974, including NMAC, (From 391 to 859 in Bethesda alone)• 2) Space - Increase of floor area from 230,000 sq,ft, (NLM Bldg.) by 218,000 sq,ft. (LHNCBC Bldg,) to a grand total of 448,000 sq.ft, in Bethesda, ATLANTA BETHESDA 3 FEASIBILITY STUDY | LHNCBC 1967 FEASIBILITY STUDY || NMAC 1968 FEASIBILITY STUDY ||| LHNCBC / NMAC 1969 EXHIBIT 1 note : gross area of buildings in square feet. BAR CHART 4 1969 BETHESDA ATLANTA 1974 BETHESDA ATLANTA EXISTING NLM BUILDING PROPOSED LHNCBC BUILDING EXIST! NG NLM BUILDING 1 new organization plan NLM 3 birdseye perspective 2 site utilization EXHIBIT 1 A 5 3) Cost - The estimated construction cost as of July I, 1969 a) The New Structure $9,172,000 b) Site Development $218,000 c) Utilities $454,000 d) Rehabilitation of NLM $1,319,000 Note: Figures consistent only with degree of detail available in advance of actual plans - to give ’’order of magnitude” only, b. Exhibit #1A (Facing Page) 1) New Organization Plan 2) Utilization of Site 3) Birdseye Perspective B, Preface 1, In 1962 the collection of books that occupied only a few shelves in 1836 as the Library of ’’The Surgeon General’s Office” expanded into a new building of its own in Bethesda, known as the National Library of Medicine. By its very nature as a collector of books it was ever growing and for some 40 years had felt the pinch of restricted quarters. It now had a facility large enough to meet its overall requirements, with an allowance of space to meet the anticipated stack expansion for the next 20 years, 2, -For years the National Library of Medicine had been in the forefront of technical advances in the adoption of new equipment and methods to library purposes. Its development of the mechanization of the photo reproduc- tion of an article from the volume in the stack to its deposit in the mail drop has been an outstanding performance, 3, Particularly notable, however, was the continued technical advance over the years in the preparation of the Index Medicus, a monthly publication listing the significant citations from some 2500 medical journals. With the installation of a computer, in the northwest corner of the building, a new automated system took over the production of the Index Medicus in a program called MEDLARS (for the Medical Literature Analysis & Retrieval System). With the aid of the computer the information extracted from the journals was stored on tapes, retrieved at the proper time and edited in a form ready for the printer. The success of this new operation opened a vast new field in usefulness of catalog and bibliography. Several additional types of services became possible, including demand bibliographies and recurring bibliographies on selected subjects. 4, With the Medical Library Assistance Act in 1965, a new and expanded role for the National Library of Medicine was established, a role embracing new functions to match the ever increasing magnitude of its already established mission. The rapid development of computer and automation techniques in the field of business, science and the military services await only the spec- ifications of the library field to harness them to a new essential purpose in our national life. The access to medical knowledge, the selection of the item, the dissemination to the user whether a library, hospital or individual doctor, becomes possible with a speed and range inconceivable a few years ago. To meet the pressures and increasing demands,the National Library of Medicine began expanding its programs and its personnel. All this had to be at the expense of space intended for the traditional library purposes for which it was founded. Additional rented space was acquired on the outside, 5, The National Library now has a far greater task to accomplish in expanding its services as the National Library of Medicine to that of a bio-medical communica- tions center for the whole country as well, performing research and development on new methods for handling information and providing new as well as traditional information services. 6, The House of Representatives Committee on Appropriations in its report on the 1967 appropriation bill directed the Library to develop a research capability and added funds to the budget for ’’development and direction of the Library’s application of advanced technology to biomedical communication problems; for studying the application of library and related learning resources to the continuing education of health scientists and practitioners; and for planning and development of the Library’s role as a center for bio-medical communica- tions.” The late Congressman John Fogarty, Chairman of the House Appropriations Sub-Committee on Labor and Health, Education, and Welfare, in a speech in 1965, suggested the establishment of a National Center of Bio-Medical Communications as a component of the Library 6 which would be closely and continuously concerned with research and development in the bio-medical communica- tion field, providing a national focal point for research in the communications and information processes themselves. This requirement was further recognized by the President’s Science Advisory Committee in its report, "Handling of Toxicological Information." 7. In response to a delegation of responsibility from the President to the Secretary of Health, Education and Welfare and subsequently to the National Library of Medicine, the Library is required to develop and operate an action-oriented Toxicological Information Exchange to meet the urgent need for a coordinated, comprehensive, computer-based file of toxicology information, 8. On August 3, 1968 President Johnson signed into law (P.L. 90-456) legislation designating^this Planned National Center for Biomedical Communications as the Lister Hill National Center for Biomedical Communica- tions honoring the "Health Statesman" Senator from Alabama• 9. The law had been introduced as Senate Joint Resolution 193 by Senator John Sparkman "to perpetuate the name of the man who has done so much for the health of the nation,” 10, Effective 1 July 1967 the National Medical Audiovisual Center (NMAC) of the PHS in Atlanta became a component part of the NLM. To carry out its new assignment as part of the NLM in the bio-medical communication field it will also require substantially increased facilities, 11, In October 1967 a Feasibility Study (11-1968) was authorized to survey the current useage of the NMAC and project its future space requirements, comparing the alternatives of remaining in Atlanta or moving to Bethesda, 12, As a result of Feasibility Study 11-1968 it was recommended the NMAC relocate in Bethesda in the NLM site. The main reasons were: a. By being in one place duplication of certain administrative and service facilities could be avoided with a resulting saving of space. b. Certain educational facilities could be shared such as seminars, auditorium space, equipment, etc,, again avoiding space duplication. c. The overall services of the LHNCBC would be enhanced and efficiency promoted by having the NMAC as a functioning part of their activities on the same site. 13* It was further recommended, in the interest of greater efficiency and economy, the two projects be combined in one new building for the LHNCBC. 14. With subsequent modifications of program, restrictions on obligations and program growth for all national projects, as well as in the interests of federal economy, it was concluded that the two projects should be examined for possible combination in one building. For this reason Feasibility Study III was authorized 20 November 1968, On 5 February 1969, however, it was decided that, because of the strong possibility the NMAC will remain in Atlanta this report, already under way, should be modified accordingly0 11• general A, Authorization Contract No. NLM 69-5 - entered into the 20th day of November 1968 by the United States Government and O’Connor & Kilham, Architects in the City of New York, amended as of 7 March 1969. B, Character and Extent of Services 1• Project Description; Initially a study of the physical requirements and estimated costs for the construction of the proposed additional facilities for the National Library of Medicine combined with the National Medical Audio- Visual Center but amended to omit the NMAC as part of the program. 2. Scope of Work "to combine in one building the require- ments of the National Library of Medicine including the National Medical Audiovisual Center, already examined in two previous studies for the purpose of accommodating the total space requirements of the present and planned programs of the National Library of Medicine in the most efficient manner.” It is to be noted subsequent cut-backs by the government required extensive re-examination of the programs of these two previous studies. Then, by amendment, as noted above, the NMAC was omitted from this project. The program is detailed in the '•Scope of Work" furnished as part of the contract as detailed hereinafter in section III. 7 3, Time of Performance Complete and delivered by March 21, 1969, an extension of time from March 1, 1969, C. Background Information 1 • NLM a. Location The National Library of Medicine is located on Wisconsin Avenue in the SE corner of the National Institutes of Health Reservation in Bethesda, Maryland, across Wisconsin Avenue from the National Naval Medical Center, b. Existing Building 1) The present building of the NLM was first occupied in 1962 as a traditional medical library. The library was formerly the Armed Forces Medical Library first under way in 1836 as the Library of the Surgeon General’s Office, The computer-based Medical Literature Analysis and Retrieval System (MEDLARS I) was installed, with resulting altera- tions, in 1963, 2) With the Medical Library Assistance Act of 1965 an increase in personnel was authorized commensurate with new program responsibilities - with still further alterations in the plans, 3) Workloads and maintenance requirements have long exceeded the design characteristics of MEDLARS I, Accordingly, the Library determined in 1966 to develop a replacement system, MEDLARS II, which could take advantage of the advances in computer technology to provide an increased capability to the Library’s programs, MEDLARS II will be implemented in three phases, a) Level 1, to be operational by the end of September 1969, will replace the capabilities of MEDLARS I, b) Level II development is scheduled to begin in mid 1969, Level II will provide for improved support to Library functions, c) Level III will provide for continued improve- ments for Library operations with an integration of the system into the biomedical communications network. It is anticipated that the total MEDLARS II will be operational by the end of 1971, Co Rented Space In June 1966 commercial space was leased in the Blackwell Building, Bethesda, to accommodate the staff of the Extramural Program, d. Future Requirements 1) The success of the MEDLARS installation as a tool of bibliographic research, the enlarged scope of collecting activities, the broad responsibilities of the NLM under the Medical Library Assistance Act of 1965 affecting the Extra Mural Program, the center for toxicological information, the authorization to proceed with the development of a sophisticated graphic image storage and retrieval system, the preservation microfilming program, the program of research and development in new system and techniques relating to the intended communication of bio-medical information, are all beyond the scope of the library of 1962 - and all have combined to create an ever increasing demand for space to house the growing staff and their activities - currently met at the expense of the space allowed for the basic library functions of the NLM and the growth of its collection and by renting commercial space, 2) To determine a physical program to best meet these demands and make due allowance for their probable development in space requirements over the next twenty years - as far as it could be reasonably projected - an initial Feasibility Study was authorized and prepared in 1967 (I - Blue Book) developing a requirement of 232,000 sq.ft, gross of new space with plans for renovating in the existing National Library of Medicine at a then estimated cost of $10,500,000, Reference is made to the study for certain details to avoid duplication, e, Site In its Master Plan for the NIH campus, additional space contiguous to, and largely to the south of, the NLM has been considered available by the NIH for the projected expansion of the NLM as studied herein, 2, NMAC a. Location The main facilities of the National Medical Audio- visual Center are located within the National 8 Communicable Disease Center complex in the suburb of Decatur, 7 miles northeast of downtown Atlanta, Georgia. The Distribution Center, and the Catalog- ing and Special Reference functions are located in a rented space nearby. b. Existing Conditions 1) In 1961, the National Medical Audiovisual Center, then part of the Communicable Disease Center, moved into the newly constructed Building No. 3 of the National Communicable Disease Center complex on Clifton Road in Decatur, Georgia. This 4-story building, consisting of 43,800 gross square feet, was designed to house all the functions of the Medical Audiovisual facility. 2) A substantial portion of the building was specifically designed and equipped for the prod- uction of audiovisuals including motion pictures, video tapes, and other audiovisual forms, 3) By 1966 the building was no longer adequate to meet the growing demands of space occasioned by the expansion of programs and activities, A temporary building was leased in Chamblee, Georgia, consisting of 9,100 gross square feet. Acquisition, Retention, Distribution, Cataloging and Special Reference functions were moved out of the building at Decatur and into the Chamblee Annex, At this writing the facilities in the Chamblee Annex have been transferred to larger quarters in rented space closer to the NMAC building, 4) Effective 1 July 1967 this Audiovisual Facility of the Public Health Service became a component part of the National Library of Medicine in Bethesda and was newly designated the National Medical Audiovisual Center, c. Present Size of NMAC and Proposed Expansion 1) The present National Medical Audiovisual Center employs 126 persons and occupies a net area of 34,010 square feet of useable space, 2) Feasibility Study II - 1968 (Gray Book) proposed an expansion to 91,430 sq.ft, net space for location in Bethesda, reduced to 82,700 sq.ft, net in updating the requirements herein. 3) The initially proposed consolidation in the LHNCBC building would have required a further reduction to 65,000 sq.ft» net or 109,000 sq.ft, gross floor area under the latest program - the balance to be provided in rented space. d. Site 1) Bethesda, If the NMAC program is consolidated with the expansion program of the NLM it would become a part of the proposed LHNCBC building to the south and connected to the existing NLM, 2) Atlanta. If the NMAC remains in Atlanta, the expansion would presumably be an addition to the East to the space currently held in Bldg. No. 3 of the NCDC, as indicated in Feasibility Study 11-1968 - unless a new site is required. D. The Need The need to expand the Library's physical facilities to meet its new responsibilities as an active research and development center is now critical. Additional space is required not only to establish the new programs but also to accommodate the expansion of current programs and to permit restoration of original library space to the National Library of Medicine for traditional library purposes, E, Information Furnished 1. By NLM a. Statement of Scope of Work for present Study and Amendment• b« Organization charts. c. Statement of NLM Organization and Functions. d. NLM Preliminary Program and Financial Plan 1970-1974, e. Planning Documents for the Biomedical Communications Network. f. Request for Proposal on Graphic Image System. g. Statements on Microfilming Programs and Film Vault Capacity. h. GSA - HEW Office Space Formula, 9 2• In^QrmaiiQn Available to Architects a. Original plan of NLM as of 1963 and of subsequent alterations to include MEDLARS I installation, Billings auditorium, and lunch room, b. Plans for MEDLARS II and recent renovations on "C" level• c. Feasibility Study (1967) New Facility for NLM. d. Feasibility Study (1968) Expansion and Location NMAC, e. Program of proposed Fogarty International Center for Advanced Study in the Health Sciences, F. Meetings 1• October 10th 1968 a, Messrs, Russell, Hill, Styers (NLM), Koester, Stephens (RFPB-NIH) and Chu (O'C & K), Preliminary planning of Study, 2. October 28th 1968 a, Messrs, Hill, McGroarty and others (NLM), Chu and Wright (O'C & K), General information meeting; collection of building field data, 3. November 14th 1968 a, Dr. Cummings, Messrs, Hill (NLM), Kilham and Chu (O'C & K), General policy meeting, b, Messrs, Waters, Miller, Bagg, Hill (NLM), Kilhara and Chu (O'C & K), Meeting on microfilming program and proposed Graphic Image Storage and Retrieval System, c, Messrs. Asch, Smith, Hill (NLM), Kilham and Chu (O'C & K), Meeting on OCES programs and activities, d, Messrs, Smith, Costabile, Hill (NLM), Kilham and Chu (O'C & K), On growth of literature collection, e, Messrs, McCArn, Hil3 (NLM), Kilham and Chu (O'C & K), On functions and concept of LHNCBC, 4. November 20th 1968 a. Dr, Rice, Messrs, Hill (NLM), Chu and Wright (O'C & K), On functions and concept of SIS, b, Messrs, Koester, Stephens (NIH), Hill (NLM), Chu and Wright (O'C & K) , Parking, Cafeteria and Utilities, 5. December 5th 1968 a. Dr. Leiter, Messrs, Waters, Smith, Hill (NLM), and Chu (OfC & K) , Detailed review of requirements of Library Operation Division, b, Messrs, Parker, Joyce (NLM) and Chu (O'C & K), On projected LHNCBC facilities. 6, December 18th and 19th 1968 a, Messrs, Hill (NLM) and Chu (O'C & K) , Detail review of overall program requirements. 7• December 27th 1968 a. Dr, Cummings, Messrs, Adams, Hill (NLM), Kilhara and Chu (O'C & K) , Review and adjustment of overall program requirements, b, Mr, Parker (NLM), and Mr, Kilham (O'C & K), On LHNCBC facilities. 8, January 14th 1969 a. Dr, Leiter, Messrs, Smith, Hill (NLM), and Chu (O1C & K). Review of diagrammatic plans of existing building for 1974, 9, January 21st 1969 a. Messrs. Parker, Hill (NLM), and Kilham (O'C & K), Visit to the Goddard Space Center, 10, January 22nd 1969 a. Dr, Cummings, Messrs, Russell, Hill (NLM), Kilham and Chu (O'C & K), Review of schematic plans for 1974. Discussion on modification of NMAC approach, b. Messrs, McCarn, Parker, Hill (NLM), Kilham and Chu (O'C & K). On LHNCBC after visit to Sterling Institute, 11• March 6th 1969 a. Dr, Davis, Messrs. Hill, (NLM), Kilham and Chu (O'C & K). LHNCBC review. b. Dr, Cummings, Messrs, Hill (NLM), Kilham and Chu (O'C & K), Final general review. 10 G. Criteria 1• Existing NLM Bldg* Rehabilitate as basic National Library of Medicine with functions as originally authorized., 2. New Structure Develop scheme - a new structure to meet new and expanded requirements of NLM as ”Bio-medical Communications Center.” (Combined with enlarged activities of the NMAC, this, initially, required the restudy and updating of the program developed in Feasibility Studies I (LHNCBC) and II (NMAC) reducing the overall program to integrate it into requirements of one combined structure). 3• Linkage Provide proper "linkage” as part of the new con- struction so combined facilities can operate efficiently as one institution, 4, Relationships The general shape and design characteristics of the building must be harmonious with or complimentary to the present NLM facility and present and planned structures in the immediate area, 5. Future Projects Make adequate allowance for future expansion on site with indication of a possible plan. 6* Flexibility New floor space to be designed with the capability of change of arrangements of partitions and utilities to permit future departmental expansion and/or modification of layout. 7. Fogarty Center Coordinate NLM program with developments for the adjacent Fogarty Center, particularly in relation to Parking & Eating Facilities. 8. Parking Coordinate with N.I.H, overall parking program. 9• Fallout Protection Meet requirements as furnished by the Office of Civilian Defense, 10. Utilities Coordinate development with N.I.H. to determine what part of NLM project cost will be shared with N.I.H. with particular reference to any required plant expansion where new or extended utilities are required. 11 m. SURVEY A, Requirements 1. Feasibility Study. The Contract of Nov, 20, 1968 stated: "Independently and not as an agent of the Government, the con- tractor will perform a study to combine in one building the requirements of the National Library of Medicine including the National Medical Audio- visual Center, already examined in two previous studies for the purpose of accommodating the total space requirements of the present and planned programs of the National Library of Medicine in the most efficient manner," As amended 7 March 1969 (prior verbal notification) the NMAC was omitted from the project on the assumption it would remain in Atlanta, 2. Scope "Specifically, the contractor will; a. Update analysis of current and projected space needs contained in the two previous studies dealing with NLM building requirements, b. Through consultation with NLM officials and study of documents to be supplied adjust total space requirements program for 1974 developed in two previous studies to reflect current NLM growth and program plans, c. Through consultation with NLM and NIH officials adjust total space analysis performed in previous studies and total space requirements program for 1974 to reflect the exclusion of some non- program facilities, d. On the basis of the foregoing analyses, adjust- ments and consultations describe a recommended approach to the location, size and general design characteristics of a new NLM facility subject to the following constraints and using information developed in the two previous studies to the maximum extent possible. 1) The location of the facility will be within the area contiguous to the NLM considered available for this purpose in the Master Plan for the National Institutes of Health. The Contractor will consult with the Chief, Research Facilities Planning Branch of the National Institutes of Health and take appropriate cognizance of total site planning and development for the NIH campus, 2) The general shape and design characteristics of the building must be harmonious with or complimentary to the present NLM facility and present and planned structures in the immediate area. 3) The dependence of the NLM on the NIH for utilities (electricity, chilled water, hot water, etc.) must be taken fully into account. e. The analysis and recommendation required above will be consolidated in a final report which contains suitable graphic analysis, diagrammatic sketches, line perspectives and models which effectively describe relationships between specific activities and gross space requirements for those activities. The report will also contain general construction cost estimates based on similar projects performed elsewhere, but not reflecting precision cost estimating techniques usually associated with detailed design and specifications. The cost estimate will include the cost of utilities and their extension from NIH, appropriate landscaping and conversion of space in the present NLM building. One hundred and fifty (150) copies of this report will be provided,’1 Following the amendment it was agreed a schedule of the requirements of the NMAC as a separate building would be included in the Appendix. 3, Delivery Preliminary Report - on or before January 7, 1969, Final Report - on or before March 1, 1969, extended to March 21, 1969, 1*12; ASSISTANT SECRETARY HEALTH & SCIENTIFIC AFFAIRS BOARD OF REGENTS PHS SURGEON GENERAL NIH NATIONAL INSTITUTES OF HEALTH OD OFFICE OF THE DIRECTOR OCES OFFICE OF COMPUTER & ENGINEERING SERVICES OAM OFFICE OF ADMINISTRATIVE MANAGEMENT OPI OFFICE OF PUBLIC INFORMATION & PUBLICATIONS MGNT PROCESSING SUPPORT SECTION SYSTEMS APPLICATION SECTION SYSTEMS DEVELOPMENT SECTION LO LIBRARY OPERATIONS EMP EXTRAMURAL PROGRAM SIS SPECIALIZED INFORMATION SERVICES NMAC NATIONAL MEDICAL AUDIOVISUAL CENTER LHNCBC LISTER HILL NATIONAL CENTER FOR BIOMEDICAL COMMUNICATIONS BSP BIBLIOGRAPHIC SERVICES DIVISION HMD HISTORY OF MEDICINE DIVISION TSD TECHNICAL SERVICES DIVISION RSD REFERENCE SERVICES DIVISION FRD FACILITIES & RESOURCES DIVISION PTD PUBLICATIONS & TRANSLATIONS DIVISION RTD RESEARCH & TRAINING DIVISION ADB AQUISITION DISTRIB. & REFER. BRANCH ESB EDUCATIONAL SYSTEMS & DEVELOP. BRANCH PB PRODUCTION BRANCH SDS SERVICES DEVELOPMENT STAFF NEB NETWORK ENG COMMUNICATION & OPERATIONS BRANCH NPB NETWORK PLANS & MANAGEMENT BRANCH CRB CUSTOMERS PRODUCTS & SERVICES DEVELOP BRANCH DLS DRUG LITERATURE SECTION TIS TOXICOLOGICAL INFORMATION EXCHANGE STAFF RDB RESEARCH & DEVELOPMENT BRANCH A EXHIBIT Z 1968 ORGANIZATION CHART 13 B. Activities of NLM 1• Activities The National Library of Medicine: a. Assists the advancement of medical and related sciences through the collection, dissemination, and exchange of information important to the progress of medicine and health; b. Serves as a national medical information resource for medical education, research, and service activities of Federal and private agencies, organizations, institutions, and individuals; c. Publishes and distributes guides to medical literature and audiovisual materials in the form of catalogs, indexes, and bibliographies; d. Develops, produces and disseminates indexes and bibliographies; e. Develops, produces and disseminates audiovisual materials and systems and other aids to medical education, research and practices; f. Supports the translation and publication of biomedical literature; g. Provides support for medical library development and for training of biomedical librarians and other health information specialists; h. Conducts and supports research in techniques and methods for recording, storing, retrieving, and communicating health information; i. Provides technical consultation services and research assistance. 2, Organization See Exhibit 2. (Facing Page) 3. Departmental Activities a. Office of the Director - OP. 1) Directs and coordinates library activities. 2) Advises the Surgeon General on PHS policy relating to the management and control of biomedical communication media. 3) Studies, identifies and defines needs in biomedical communications. 4) Provides the secretariat for the NLM Board of Regents. b. Office of Public Information and Publications Management - OPT. 1) Provides information services for the bio- medical community and for the general public on NLM programs, services and products and on biomedical communications through press releases, pamphlets, exhibits and other media. 2) Coordinates the publication and distribution of NLM publications. c. Office of Administrative Management - QAM. Provides overall management and administrative services for the Library. d. Office of Computer and Engineering Serviced- OCES. 1) Performs systems analysis in collaboration with user organizations to determine require- ments for data processing support, and performs systems analysis and computer programming for the implementation of data processing systems. 2) Provides data processing technical interface with Medlars Centers. 3) Maintains operating systems. 4) Operates and maintains digital computer phototypesetting and related data processing storage retrieval and transmission equipment. 5) Establishes production schedules and performs production control for NLM machine based operations. 14 6) Produces and distributes magnetic tape to MEDLARS Search Centers and other authorized users in the United States and abroad. e. Office of the Associate Director for Library Operations - LO. 1) Administers the Libraryfs direct operations. 2) Analyzes and evaluates direct operations in relation to program needs. 3) Plans and administers a national biomedical library network. f. Office of the Associate Director for Extramural Programs - EMP. 1) Administers programs to augment and strengthen the health sciences libraries of the nation and to improve biomedical communications through grants to, or contracts with, non- federal and private institutions. 2) Analyzes and evaluates extramural programs in relation to program objectives and national needs to achieve balanced and effective support. 3) Provides grants management, grants processing, and administrative management services. g. Office of the Associate Director for Specialized Information Services - SIS. 1) Coordinates the development and operation of specialized information services throughout the NLM, 2) Plans, develops and operates a national toxicological information system. 3) Develops and administers a program to organize and analyze published information on the effects of drugs and chemical on man, and prepares special bibliographies and reports on that subject. h. National Medical Audiovisual Center - NMAC-Atlanta 1) Office of the Associate Director for Audio- visual Telecommunications. a) Plans, directs, coordinates, and evaluates a national program in biomedical audio- visual and telecommunications; and b) Provides program management support for the National Medical Audiovisual Center. 2) National Medical Audiovisual Center (Atlanta), a) Operates the central facility in the Public Health Service for the development, production, distribution, evaluation, and utilization of motion pictures, video- tapes, and other audiovisual forms. b) Coordinates a comprehensive audiovisual program for the Service to assure maximum responsiveness and economy of funds and manpower. c) Provides consultation and assistance in the development of specialized audiovisual activities. d) Encourages the production, dissemination, and utilization of medical films and other audiovisuals in the schools of health professions and elsewhere. e) Operates a national clearing house and archival program. f) Acts as a national/international film and videotape center for the distribution and exchange of biomedical audiovisuals. i. Lister Hill National Center for Biomedical Communications - LHNCBC. 1) Designs, develops, implements, and manages a Biomedical Communications Network. 2) Assists the biomedical community in identifying and developing products and services for dissemination through the net- work . 15 3) Develops networks and information systems to improve health education, medical research, and the delivery of health services. 4) Applies technology to the improvement of bio- medical communications, 5) Represents DREW in Federal activities related to information communications activities, 6) Serves as the focal point in the Department for development and coordination of biomedical communications,systems, and network projects, 4, Growth of Activities - 5 year plan - 1970-74 In accordance with the reorganization of health activities in the Department of Health, Education, and Welfare, the National Library of Medicine will continue to serve as the Department's vital center for health communications and related scientific information systems development. Objectives: a. Support, strengthen, and encourage the develop- ment of the Nation's health information resources, 1) The NLM has developed a health information network concept which involves public and private health information resources and activities in an integrated national system, 2) The NLM will support and strengthen bio- medical libraries and related institutions, build on and strengthen existing relation- ships between institutions involved in health communications, and take steps to enhance the role of the library as a learning resource center , b. Expand and improve current library services at the NLM to provide back up to the national net- work and regional services to the Middle Atlantic area. The NLM will serve as the ultimate backstop in the national medical library network. To do this, NLM will expand levels of bibliographic, reference, and loan services. The Library will also serve as the regional medical library for the Middle Atlantic area. To achieve this objective during the period 1970-1974, intramural efforts will be directed toward: 1) Converting the present computerized Medical Literature Analysis and Retrieval System (MEDLARS) to an enlarged and expanded capability second-generation system (MEDLARS II); 2) Application of new techology to graphic image storage and retrieval and the develop- ment and installation of a prototype system; and, 3) Continued development and conversion of traditional library operations to automated systems. All efforts must be conducted concurrently for maximum effectiveness. The main thrust (and heaviest funding requirements) of MEDLARS II development will occur during the period 1969- 1972, while the mechanization of library opera- tions and graphic image storage and retrieval development activities will occur in 1970 and 1971. c. Provide rapid dissemination of biomedical information through audiovisual modes. To accelerate the transfer of biomedical informa- tion and to augment existing media and human resources, present audiovisual capability will be upgraded and new modes will be developed for use in schools of the health professions, for continuing education of health scientists and practitioners, and for upgrading the health knowledge of the general population. The main effort in achieving this objective will come from activities of the National Medical Audiovisual Center directed toward man- power development and training and improved communication of health information. 16 Direct funds will be used to provide: 1) Demonstration projects which can serve as prototypes for the utilization of new audiovisual concepts and media applications* 2) Technical assistance and advice to schools of the health professions in developing audiovisual capabilities and applying new technology * 3) Regional training conferences and seminars* 4) Expansion and systems integration of audio- visual material cataloging and bibliographic services with MEDLARS. d. Develop and operate a computer-based national toxicological information system. The NLM will develop and operate a comprehensive information system on toxicology, promote concensus on standards for use in health related information systems and respond to incoming requests for stored information, directly or by referral, and provide or arrange repackaging of stored material. The first phase of this effort which is now in progress and will extend through 1970 is con- cerned with program planning and systems engineering and development to be accomplished through closely directed and monitored contracts to identify potential users of the system, identify sources of information to be used in compiling data banks, and develop specifications for a computer-based information system. Later phases of the toxicology information program effort will be directed to experimental and pilot provision of services, system installa- tion and actual operations. e. Develop and operate a research and development program in biomedical communications. The LHNCBC will design and develop communications systems, apply technology to operational problems and apply advanced communications technology along with other relevant technologies to implement a comprehensive public health services informa- tion network. During the 1970-1974 period a highly skilled staff of information scientists and systems specialists will plan, design, and develop with contractual support a health information net- work. Also, during the first three years of the period the LHNCBC will be involved in the development of the full range of MEDLARS II technical capabilities, systems engineering and technical design of the computer-based toxicology information program, and the design and development of communications linkages between components of the emerging national medical library network. 5, Photographs Photographs 1 thru 18 on pages 32 & 33 show various aspects of existing conditions and activities at the NLM as noted by captions, C. Present Conditions 1. Project Location - Site Plan of N.I.H. - 1969 See Exhibit 3, facing page. This plan shows the location of the project in the southeast corner of the National Institute of Health Reservation on Wisconsin Avenue in Bethesda. The existing NLM is indicated by Number 38. The plan further indicates: a. New Virus Laboratory #41, b. Site of proposed Fogarty International Center for Advanced Study in the Health Science #45, c. Buildings with Eating Facilities within the Reservation - indicated by symbol "C", 2. Project Site Plan of N.L.M. - See Exhibit 4, page 18. a. Nearby parking areas of N.I.H, Additional parking areas under study by N,I,H, b. Existing Utilities subject to new connections. Steam and chilled water are in tunnel - electricity in conduit. Water & sewage are public utility, use of which is negotiated for directly by NLM, 11 BOILER PLANT & REFRIGERATOR PLANT 38 NATIONAL LIBRARY OF MEDICINE 41 NEW VIRUS LABORATORY 45 PROPOSED FOGARTY CENTER (cheating FACILITIES EXISTING BUILDINGS FUTURE BUILDINGS EXHIBIT 3 1969 SITE PLAN OF NIH 18 EXHIBIT NLM SITE PLAN 19 c. N.L.M. Parking (West)* An interim use of space reserved for major stack expansion now full to capacity. d, NLM Parking - Visitors (North). Too small for present conditions, e, NLM expansion site (southwest) proposed for this project, f. "Greenbelt”, Area surrounding N0I,H0 Reservation, To be kept free of buildings or screening structures• 3• Facilities off N,I,H, Site a. Blackwell Building, Bethesda. Space rented. b. NMAC - Atlanta, 4, Lunch Room Facility, MA" Level To be retained for box lunches from home, particularly for public working in library on Sundays when usual eating facilities are closed. New facilities to be available at proposed Fogarty Center, 5, Utilities a. Water - Public Utility (Washington Suburban Sanitary Commission) - direct connection, b* Sanitary Sewer - Public Utility (Washington Suburban Sanitary Commission) - direct connection. c. Storm Water - direct outlet to brook, d. Steam - obtained from N.I.H, Central Power Plant, Bldg. #11. e. Chilled Water - obtained from N,I0H, Central Power Plant, Bldg, #11. f. Electricity - connected to present feeders serving N.L.M. g. Telephone - Chesapeake & Potomac Telephone Co, 6• Foundation Conditions Solid rock - as indicated by borings available from construction of NLM and present new Virus Laboratory, 7, Zoning, Codes, and Controls a. National Capital Planning Commission, b. Montgomery County Zoning Ordinance (1960) does not place restrictions on government buildings, c. National Building Code (N B F U), d. N.I.H, Office Committee on Fire Safety. e. National Electrical Code (N B F U), 8. Existing Floor Plans of NLM See Exhibits 5 through 9, pages 20 through 24, following. 20 BOARD ROOM EXHIBIT 5 1969 MEZZANINE FLOOR PLAN 21 EXHIBIT 6 1969 FIRST FLOOR PLAN EXHIBIT 7 1969 A LEVEL PLAN EXHIBIT 8 1969 B LEVEL PLAN 24 EXHIBIT 9 1969 C LEVEL PLAN 25 P 19v69 Area P 1974 Area c• (LO) Assoc. Dir, Lib, Operations i) Office of Assoc, Director 7 960 34 4,300 2) Technical Service Div, 57 12,820 93 17,070 3) Reference Service Div. 69 13,470 121 22,060 4) Bibliographic Services Div, 61 8,050 102 15,050 5) Hist, of Medicine Div, 18 7,600 30 8,590 6) Special Pur- pose Spaces 93,020 130,640 212 136,020 380 197,710 D, Five Year Expansion 1. Projected Expansion of Personnel & Space Requirements Summary; 1969 1974 P Area P Area a. (OD) Office of Director i) Office of the Director 10 3,470 13 3,590 2) Admin, Mngmt, 32 9,430 50 19,240 3) Pub, Info Pub, Management 6 2,190 9 1,530 4) Common 6,260 10,820 48 21,310 72 35,180 d. (EMP) Extramural Programs 1) Office of Assoc, Dir, 19 2,440 36 4,360 2) Publications & Translations 4 760 18 2,220 3) Research & Training 3 610 18 2,270 4) Facilities & Resources 12 1,660 18 2,450 5) Special Pur- pose Space 940 1,870 38 6,410 90 13,170 b* (OCES) Computer Eng• Ser* 1) Office of the Chief 8 1,600 9 1,880 2) Systems Development 8 2,040 17 3,260 3) Processing Suppor t 32 5,880 28 8,510 4) Systems Application 10 2,880 17 2,850 58 12,400 71 16,500 26 1969 P Area 1974 P Area (SIS) Specialized Info Services 1) Office of Assoc. Dire 3 650 20 2,560 2) Toxicology Info Exchange 1 180 60 7,690 3) Services Development 9 1 ,050 47 5,950 4) Drug Literature Program 7 630 19 2,310 5) Common Space 580 1,800 6) Other Personnel 140 20 3,230 146 20,310 2. Types of Space Required For the purposes of estimating costs at this time the following general categories of space have been determined, a. Office space - offices, work rooms and conference rooms with normal requirements. b. Technical spaces - office type work spaces with additional power outlets and/or mechanical system to provide for special lighting, use of special audiovisual or camera equipment, etc. c. Laboratory space - work space with special requirements for plumbing, mechanical, electric and/or other services. Photographic dark rooms for example. d. Classroom space - places of assembly for con- ferences, seminars and instructional purposes. e. Special purpose space - space specifically designed for and equipped for special purposes such as computer space and Communication Net- work Center, (LHNCBC) Lister Hill Nat. Center 1) Office of Director 5 980 11 3,190 2) Plans & Management 2 300 17 2,370 3) Research & Development 2 410 17 7,660 4) Network Engineering 3 700 35 20,310 5) Customer Prod- ucts & Services 3 450 20 4,520 6) Reference Facility 0 0 2,500 7) Antenna Facility 0 2,050 15 2,840 100 42,600 TOTALS a, b, c, d, e, fo 391 182,210 859 325,470 f. Storage space. 3. Departmental space allocations. See Exhibits 10 & 11, — c Pages 27 & 28. a. With the construction of the LHNCBC certain non-traditional library departments will move to the new center permitting expansion of certain library and NLM administration within the existing building. However, additional space for MtraditionalM library departments will still be required in the new building, b. Some stack space will be required and more will be made available in the new structure to take care of expansion for 20 years until 1989, with provision reserved for major stack expansion taking place at a later date in the area immediately west of the NLM building, as originally intended. It is now used for parking, c. Exhibit 12, page 29, shows the expanded program in diagrammatic form and indicates those facilities which will remain in the NLM and which will be located in the new LHNCBC, For complete breakdown see Appendix I, IN NEW 8UILDINC ' FACILITIES \H ATLANTA- " FACILITIES IN EXISTING BUILDING. LHNCBC SIS OD OFF OF THE DIRECTOR NMAC EMP 10 NETWORK training LO NETWORK MANAGEMENT OPI OAM OCES COMPUTER, ETC BSD INDEXERS MEDLARS BIBLIOGRAPHIC SEARCH REFERENCE SERVICE WORK AREA INTER-LIBRARY LOAN & PHOTO DUPLICATION CONFERENCE ROOM :|||( TECHNICAL SERVICE AUDITORIUM HISTORY OF MEDICINE CATALOG READING ROOM GRAPHIC IMAGE STACKS STACKS MICRO-RECORDS SUPPLY PRESERVATION BINDING Rtcmm & MAIL LUNCH ROOM RECEIVING & MAIL EXHIBIT 10 ORGANIZATIONAL RELATIONSHIP DIAGRAM LHNCBC LHNCBC FACILITIES • yill; IN NEW BUILDING OD DIRECTOR CURRENT FACILITIES LISTER HILL NATIONAL CENTER FOR BIOMEDICAL COMMUNICATION SIS EMP LO NETWORK MGNT BSD PUBLIC INFORMATION OAM ADMINISTRATIVE MGNT SIS SERVICES INFORM, SPtCIAUEEO • • t • • m • • BSD INDEXERS BSD SEARCHERS OCES IMP * EXTRAMURAL * PROGRAM COMPUTER NETWORK TRAINING DATA PROCESSING CONFERENCE ROOM SYSTEMS ANALYSTS REFERENCE SERVICES WORK AREA CATALOG BSD poblio OCES COMPUTER DATA PROCESSING SYSTEMS ANALYSTS INDEXERS TECHNICAL SERVICE MEDLARS AUDITORIUM READING ROOM HISTORY OF MEDICINE LOBBY PUBLIC HMD STACKS PHOTO DUPLICATION SERVICES SUPPLY STACKS STACKS GRAPHIC IMAGE BINDING MICRO-RECORDS SUPPLY SYMBOLS RECEIVING RECEIVING LUNCH ROOM RELATED FUNCTION J FUNCTION TO BE RELOCATED IN NEW BUILDING EXHIBIT 11 SICAL RELATIONSHIP DIAGRAM 29 EXHIBIT 12 PROPOSED NLM PROGRAM FOR 1974 (BETHESDA) 30 4. Special Consideration a. Linkage 1) To preserve the integrity of the NLM in its aspect as distinctive building on the NIH campus, and to avoid disturbance of already established public areas on the main floor, it is proposed the new and old buildings be connected only at "A" level and below. "A" floor also has the advantage of space pro- visions overhead for extending duct and conduit work, computer cable connection, etc., and providing access for service entrance for interchange of mail and deliveries. 2) The "A" level would also be the principle passage for personnel traffic permitting the most convenient circulation to facilities used in common in either structure such as auditorium, conference rooms, lunch room (for people bringing own), as well as inter- departmental activities, b. Growth of Collections 1) Literature Collections, Exhibit 13, page 31. a) Mission. The basic mission of the NLM includes the acquisition of the published literature of the bio-medical sciences, and these will continue to be housed in the stacks of the original building (subject to extension as required). It is assumed that for the next 10-20 years (while new types of medical information forms are developing) books and journals will continue to be the principal means of communication. b) The apparent growth rate - estimates based on the linear feet of occupied shelving indicated the present collection is doubling every 15 years or so. c) Changes in scope of collection - with its new role in the national health effort the library not only faces a rapid expansion of its basic programs utilizing the book collection but now faces the need of a collection of bio-medical literature with a much broader coverage in subject matter in fields related to problems of health and education* In addition the total body of medical literature today is expand- ing at a faster rate. For this reason, the rate of growth in- dicates not only the increase from the acquisition of newly published bio-medical literature but also the acquisition, for the first time, of books in the broader field including the related subjects. It is anticipated this expansion of the scope of the collection, added to the normal rate growth, will double the collection every 14 years. d) Normal Stack Expansion The plans of 1962 allowed for a stack expan- sion within the structure of approximately three times the entering collection - or the equivalent of 159,400 lin.ft, of shelving. Much of this reserve for expansion has been encroached upon not only by unexpected growth in the ’'traditional" library depart- ments because of the demands on their in- creasingly valued services but particularly by the space required for the new services that have become possible with the use of the computer plus the development of new areas required for the effective use of the computer itself - such as systems analysis, programming, data processing and problems of indexing - in the MEDLARS program. As of 1969 all this has reduced the ultimate stack capacity to 122,000 lin.ft. Even if these later departments and the computer move out into the new structure and the library is restored to its traditional purposes it will be found that considerable stack space has still been lost to other purposes. Exhibit 13, page 31, indicates 31 the total ultimate stack capacity of 1962 of 159,400 lin, ft, will be reduced to 134.000 lin. ft, after the 1974 program. Assuming the rate of growth figures avail- able at present, 5%, this indicates the present stacks will be full by 1981, If expansion is to be allowed for within the new project until 1989, (20 years from 1969) this means five years more of growth should be allowed for in this program - approximately 63,800 lin. ft, of stack, a grand total of 197,800. To achieve this it is proposed to provide 39.000 lin.ft. of standard stack in the new building bringing the total to 173,000 lin.ft, and, in addition, putting one- quarter of the collection in compact storage on "C" level in the old building, thus gaining the balance of the 24,800 lin, ft, required for 1989, 2) Microfilm Collection a) Microfilming is still the only feasible method for preserving the printed record of biomedical progress. The five year program submitted March 11, 1968 called for conversion of 62 million pages, about 20% of the total pages in the NLM collection. During this five-year period the collection will grow by 75 million pages, b) The film vault is now completed and has a maximum capacity of 94,000 reels and an effective capacity of 75,000 reels. By the end of FY 1969, 20,300 reels of print- ing masters and security films will be stored in the vault. The 62 million pages requested in the five-year plan will add 80.000 reels of security and printing masters to the collection. Realization of a program of this size beginning with FY 71 would mean that the effective capacity of the vault would be reached by FY 74. STACK CAPACITY EXISTING AND NEW BUILDING /(WITH COMPACT STORAGE FOR \/U OF COLLECTION) WORKING LINEAR FEET OF SHELVING (ASSUMES 15 LF WORKING CAPACITY PER SINGLE FACE STACK UNIT) GROWTH OF N LM LITERATURE COLLECTION SHELVING FIGURES DO NOT INCLUDE SPECIAL STACKS FOR TSD EXHIBIT 13 I. EXISTING NATIONAL LIBRARY OF MEDICINE, BETHESDA, MARYLAND 2. PUBLIC CARD CATALOG 8, EXISTING N.L.M. SITE MODEL 4. TYPICAL STACK AREA 5. TYPICAL STAFF AREA 6. READING ROOM - CARREL TYPE SEATING 7. MOVABLE CAMERA WITHIN STACK - PHOTOGRAPHY FROM PAGE TO MICROFILM 8. PUNCH PAPER TAPE DATA-INPUT TYPEWRITER - MEDLARS 9. MEDLARS INSTALLATION - CONSOLE & PAPER TAPE READERS 12, ATLANTA. CDC COMPLEX OF NMAC 10. EXISTING PARKING - FUTURE BOOKSTACKS 11. EXTERIOR NLM - FUTURE JUNCTURE OF TERRACE 13. FILM DISTRIBUTION - NMAC 15.. TELEVISION STUDIO - NMAC 14. SEMINARS AND WORKSHOPS - NMAC CEREBROVASCULAR SUBJECT stimulation and temperature on the contractility of the rat myocardium injured by anoxia. Krofta K, et al. Physiol Bohemoslov 14:236-40, 1965 Cit. no 1335642 The resistance of the myocardium to anoxia in animals acclimated to simulated altitude Poupa O, et al Physiol Bohemoslov 14:233-7, 1965 Cit no 1335641 Polycythaemia in neoplastic diseases Penington DG. Proc Roy Soc Med 58:488-90, Jul 65 Cit no 1273333 Coronary artery enlargement in the hypoxic white rat. Kerr A Jr, et al Proc Soc Exp Biol Med 119:717-8, Jul 65 Cit no 1331646 Radiation response of mammalian cells grown in culture V. Temperature dependence of the repair of x-ray damage in surviving cells (aerobic and hypoxic). Elkind MM. et al Radial Res 25:359-76, Jun 65 Cit no 1210742 Influence of moderate hypoxia in one lung on the distribution of the pulmonary circulation and ventilation Arborelius M Jr. Scand J Clin Lab Invest 17:257-9, 1965 Cit. no 1277755 Blood sludging and tissue destruction in burns Berkeley WT Jr Southern Med J 58:1182-4, Sep 65 Cit no 1341730 Management of diabetic patients during surgery. Packovich MJ, et al. Surg Clin N Amer 45:975-82, Aug 65 Cit no 1257102 Untoward ophthalmic and neurologic events of anesthesia Terry HR Jr, et al. Surg Clin N Amer 45:927-38, Aug 65 Cit no 1257076 Anaesthesist 13:337-40, Oct 64 (Ger) Cit no 1277203 [Construction and use of the hyperbaric oxygen chamber] Rodewald G, et aJ Anaesthesist 14:100-3, Apr 65 (Ger) Cit. no. 1271451 [On the problem of the hepatotoxicity of halothane Animal experiments with special reference to hypoxia doses] Schweikert CH, et al. Anaesthesist 14:74-9, Mar 65 (Ger) Cit. no 1210033 [On evaluation of the contractility of the myocardium The duration of systole and its correlation under different hemodynamic and myocardial conditions) Hegglin R, et al. Arch Kreislaufforsch 46:17-27, Mar 65 (Ger) Cit no. 1236653 [The determination of anoxia tolerance in rat heart-lung preparations and the influence of coronary agents on them] Kukovetz WR Arzneimittelforschung 14:1104-7, Oct 64 (Ger) Cit no 1367702 [Hypoxia and metabolic disturbances in plasma cell interstitial pneumonia of premature and undernourished infants] Varga F, et al Cesk Pediat 20:317-9, Mar 65 (Ger) Cit no 1274041 [Direct cortical stimulus-response, impulses and polyneuronal activities during hypoxia} Wieck HH Deutsch Z Nervenheilk 186:299-322. 5 Oct 64 (Ger) Cit no 1311627 [Isthmus blockade and hypoxia as causes of chronic recurrent and acute tryptic pancreatitis) Wanke M Gastroenterologia (Basel) 103:103-18, 1965 (Ger) Cit no. 1210367 [The influence of 02 deficiency on the development of 16. INDEX MEDICUS 17. SAMPLE PAGE, INDEX MEDICUS 18, CONVERTING CARD CATALOG TO COMPUTER TAPE. WESTERN RESERVE, 19. MOCK-UP OF AUDIO-VISUAL CARREL 20. EX. GRAPHIC IMAGE STORAGE & RETRIEVAL - "SELECTRIEVER" 21. CONSOLE ASSEMBLY, M.I„T, LIBRARY COMPUTER ACCESS. 22. COMPARISON OF STANDARD AND COMPACT STACK. 23, ELECTROCOMPACT STACK. AMERICAN UNIV. WASHINGTON D.C. 24, PROJECT RISC AT NLM. 25. AV INSTRUCTIONAL EQUIPMENT CONTROL CENTER. 26. AV EQUIPMENT CENTER SERVING 3 SPACES. STERLING INST. 27. PROPOSED TERRACE - LHNCBC 28. COMPUTER INPUT. M.I.T. LIBRARY 29. GRAPHIC IMAGE STORAGE & RETRIEVAL. M.I.T. 30, CONSOLE MOCK-UP FOR LIBRARY AT M.I.T. 31. MEDICAL RESEARCH CENTERS SERVED BY N.L.M. (MEDLARS CENTERS FLAGGED} 33. COMMUNICATIONS NETWORK CONTROL. GODDARD. 32, INTERNAL CONTROL CENTER. GODDARD SPACE CENTER 35. MODEL, LHNCBC, FROM S.W. 36. MODEL, LHNCBC, SHOWING FUTURE EXPANSION. 34. MODEL, LHNCBC,FROM WISCONSIN AVE. S.E. 36 c. Automated Graphic Image Storage, Retrieval and Print-out Device. 1) The Reference Services Division of the National Library of Medicine presently receives over 150,000 requests annually to lend copies of journal articles to other libraries. An article may consist of one to one hundred pages. 2) Their present objective is to obtain an auto- mated system capable of rapidly locating desired documents in microform from a file, and making a distribution copy of the requested items. The initial purpose of the system will be to speed up service to readers. Current journal articles that are in heavy demand will be photographed and stored in the system for quick retrieval from any of the several dis- play units that will be installed within the building, 3) The basic file should have the capacity to store between 140,000 and 200,000 articles and be capable of producing output copy of at least 500 articles in an 8 hour shift in either direct enlargement prints or on a com- posite roll of film, d. Network Engineering & Communications Center 1) One of the principal responsibilites of the Lister Hill Center for Biomedical Communica- tions is the design, development, implementa- tion and management of the Biomedical Communications Network. 2) Current efforts in the linkage of computer systems into networks continues the develop- ment first of the use of the individual computer, then followed by computer systems, 3) The proposed linking of libraries, informa- tion centers, medical schools, hospitals and research centers through communications will constitute the network, 4) The network control and management will be exercised from the Center. 5) The various services of the network will be available on a decentralized basis and accessible through local hospitals, medical societies, clinics, medical schools, medical libraries, and private offices. 6) The National Library of Medicine has isolated five cluster points of health activity which if linked via communications would inter- connect some forty percent of the physician population of the nation. These are Los Angeles, New York-Boston, Washington, D.C., Atlanta, and any one of the cities of Chicago, Houston, or Detroit. e. Communications Laboratories Facilities Related to the Communications Central would be a small series of laboratories where equipment and methods can be screened, tested, and evaluated, including demonstration areas for visitors. Alternate or more advanced systems could be set up with means of connection 'on line* to the Communications Center for performance tests, program substitutions, or as a back-up, etc. These laboratories would also maintain technical and quality control of broadcasts, maintain and service equipment, and assemble programs. Photo 24, page 34, of the RISC installation now in use in the NLM is also an example of the experimentation in advance of an essential part of the future Communications Center. f. Audiovisual Equipment 1) The NLM is already making increasing use of Audiovisual equipment with a particular view to gaining experience for the grant program that will become possible with the new LHNCBC. 2) The microfilm program is not only concerned with the preservation of documents but also with the putting of certain medical literature into a form that can be utilized as the first step in adaptation to requirements of various printing, facsimile or storage & retrieval devices as may be used. 37 3) Audiovisual machines using single concept films are now available in the reference reading room. 4) A T.V. installation in the corner of the same reading room permits dial access to certain programs. g. Audiovisual Production Facilities, NMAC, 1) the NMAC in Atlanta, now a part of the NLM, has the studios and other facilities for the production of audiovisuals, including motion pictures, video tapes, and other audio- visual forms. It also acquires pertinent material from other sources. Its work includes a catalog filing and distribution service. In addition it includes a rapidly developing audiovisual planning system concerned with Educational studies and development, 2) It serves as a focal point for the production, utilization and distribution of all audio- visual forms in support of the mission of the Public Health Services through the NLM, 3) Photographs 13, 14, and 15, page 33 illustrate present film distributions, instructions and production facilities. IV. DEVELOPMENT A. Program as of 1974 - Bethesda 1• Schedules For the Program in tabular form - personnel and areas - see Exhibits 14 and 14A, pages 38 & 39. For detailed breakdown see additional tables in Appendix I. 2. Diagrammatic Plans a. For comparison of space utilization in NLM Building as of 1969 and after revision to "traditional uses" in new program of 1974 see Exhibits 15 through 19, pages 40, 42, 44, 46 and 48. b. For diagrammatic plans and sections of proposed utilization of space in new LHNCBC see Exhibits ISA through 19A, pages 41, 43, 45, 47 and 49. 3. NMAC - Atlanta a. Program schedule as of 1974 for a new building, or with addition to old, totaling 96,600 net sq. ft. See Appendix II. b. If NMAC moves to Bethesda, Because certain requirements, particularly in administration and service areas, could be con- solidated with existing departments of the NLM, thereby avoiding duplication of services, the NMAC program could be reduced by 13,900 sq.ft, to 82,700 net sq.ft. c. If NMAC remains at Decatur. If the NMAC remains at Decatur in the NCDC building, 34,200 sq.ft, will be taken care of in the existing structure leaving approx, 61,400 for construction in a new addition. d. New Building. NMAC. If a new site and funds become available to the NMAC, as of 1974, it will require the complete program of 96,600 net sq.ft. 38 NIM - PROGRAM SUMMARY 1974 BETHESDA ] P L 9 6 t AREA SUBTOTAL P 1 9 AREA 7 4 SUBTOTAL Mall P I BLDG, AREA 1974 SUBTOTAL LEHC P ,BC BD AREA DG* 1974 SUBTOTAL I* (0*D.) Office of Director A. Office of Director 10 3470 13 3590 11 3130 2 400 B. Admin* Management 32 9430 50 19240 25 3670 25 15700 C* Pub* Info* Pub* Management 6 2190 9 1530 8 1240 1 530 D* 'Common Space «. 6260 _ 10820 _ 6320 4500 48 21,310 72 35,180 44 14,560 28 21,130 II* (OCES) Computer and Engineering Services A* Office of the Chief 8 1600 9 1880 - - 9 1880 B* Systems Development 8 2040 17 3260 - - 17 3260 Coprocessing Support 32 5880 28 8510 - - 28 8510 D* S/stfems Application 10 2880 17 2850 _ 17 2850 58 12,400 71 16,500 71 16,500 III* (LG) Associate Director Library Operations A* Office of Assoc. Director 7 960 34 4300 25 3740 9 1010 B. Technical Service Div. 57 12820 93 17070 93 17040 - - C. Reference Service Div. 69 13470 121 22060 121 21510 - - D. Biblio Services Div. 61 8150 102 15050 36 4710 67 10510 E* History of Medicine Div. 18 7600 30 8590 30 8420 - - F. Special Purpose Spaces 93020 130 64C L03800 - 24100 212 136,020 380 197,7i0“ 304 159,220 76 35,620 REMARKS EXHIBIT 14 PROGRAM SUMMARY 1974 BETHESDA NLM - PROGRAM SUMMARY 1974 19 6 9 1 9 7 4 M- A.IN BLDG. 1974 LHNCBC BLDG. 1974 BETEESDA - continued P AREA SUBTOTAL P AREA SUBTOTAL P AREA SUBTOTAL P AREA SUBTOTAL IV. (SMP) Extramural Programs A* Office of Assoc* Director 19 2440 36 4360 mm - 36 4360 B. Publications Trans. Div. 4 760 18 2220 - - 18 2220 C. Research and Training 3 610 18 2270 - - 18 2270 D, Facilities & Resources 12 1660 18 2450 - - 18 2450 E. Special Purpose Spaces _ 940 _ 1870 «• 1870 38 6,410 90 13,170 •• — ~ — 90 13,170 V* (SIS) Specialized Info. Service IS A* Office of Assoc. Director 3 650 20 2560 - - 20 2560 B. Toxicology Info* Exchange 1 180 60 7690 - - 60 7690 C. Services Development 9 1050 47 5950 - - 47 5950 D. Drug Literature Program 7 630 19 2310 - - 19 2310 E* Common Space - 580 - 1800 - - - 1800 F. Other Personnel 140 - • _ • 20 3,230 146 20,310 “ ~ ~ — 146 20,310 VI. (LPNCBC) Lister Hill National Center A* Office of Director 5 980 11 3190 - - 11 3190 B* Plans and Management 2 300 17 23 70 - - 17 2370 C. Research & Development 2 410 17 7660 - - 17 7660 D. Network Engineering 3 700 35 20310 mm - 35 20310 E. Customer Products & Svoes. 3 450 20 4520 - - 20 4520 F. Reference Facility - - 2500 - - - 2500 G. Antenna Facility 2050 - - 2050 15 2,840 100 42,600 — — — — 100 42,600 TOTALS 391 182,210 859 325,470 348 173,780 511 149,330 REMARKS 14a 40. LEGEND OD OAM OPI OCES LO SIS LHNCBC OPEN WELL STAIR ELEVATOR EXHIBIT 15 1969 MEZZANINE FLOOR PLAN OPEN WELL EXHIBIT 15 a SEE LEGEND ON EXHIBIT 15 1974 MEZZANINE DIAGRAMMATIC PLAN EXHIBIT 16 SEE LEGEND ON EXHIBIT 15 1969 FIRST FLOOR DIAGRAMMATIC PLAN EXHIBIT 16a SEE LEGEND ON EXHIBIT 15 1974 FIRST FLOOR DIAGRAMMATIC PLAN EXHIBIT 17 SEE LEGEND ON EXHIBIT 15 1969 A LEVEL DIAGRAMMATIC PLAN EXHIBIT 17a SEE LEGEND ON EXHIBIT 15 1974 A LEVEL DIAGRAMMATIC PLAN EXHIBIT 18 SEE LEGEND ON EXHIBIT 15 1969 B LEVEL DIAGRAMMATIC PLAN EXHIBIT 18a SEE LEGEND ON EXHIBIT 15 1974 B LEVEL DIAGRAMMATIC PLAN EXHIBIT 19 1969 C LEVEL DIAGRAMMATIC PLAN SEE LEGEND ON EXHIBIT 15 49, STACKS CONTINUE NEW BLDG EXHIBIT 19a 1974 C LEVEL DIAGRAMMATIC PLAN SEE LEGEND ON EXHIBIT 15 4, Graphic Comparison B. Specific Areas and Details 1. Growth of Bookstacks, See Exhibit 13, page 31, To accommodate the growth of bookstacks until 1989 estimated at 75,800 linear feet of additional shelving, it is proposed: a. New stack space in LHNCBC 39,000 lin, ft, with installation of the standard stack and spacing now currently in use. Insofar as practical, any standard stack displaced by plan changes in the existing NLM Building would be reused. See Photos 4 & 6, page 32, b. Compact Stacks, To gain the additional shelving various types of compact stacks were analyzed in Feasibility Study I, It is concluded the best type would be one that does not change the current method of shelving books (standard shelf arrangement), or require moving of heavy sliding, or swinging sections by hand. At this time the most satisfactory compact system would seem to be ’’Aisle - Compression Electric” type which can be seen in the library of the nearby American University, 1) This type would permit doubling the number of books in a given area and still maintain the 70% of capacity desired for ’’shelving” by the Librarian for books in active usage, 2) In the area assigned the additional 24,800 lin, ft, of shelving could thus be gained, 3) Since compaction of book storage of this type would more than double the weight on the floor, it is proposed to use the area in- dicated on ”C” level which bears on the ground, (Rock), 4) Photograph 22, Page 34, shows the system installed in an existing stack area in the American University, Photograph 23 shows how an aisle can be opened up between any pair of ranges and how the shelving is the same as in the standard stack. A bar chart showing comparison of these different alternates is indicated in Exhibit 20 below. NMAC PROGRAM ALTERNATES overlapping facilities BETHESDA I ADDITION ATLANTA mNEW BUILDING ATLANTA 5) This type of stack can now be installed above the existing floor without changes in slab by having 4" step as shown in Photo 22, note. area in net square feet. 20 NMAC ALTERNATES EXHIBIT 51 6) The layout for the assigned area on "C" level with this type of stack to permit doubling the capacity of the area is shown on plan of "C" level, Exhibit 21, page 52. For comparison, the spaces occupied by one- quarter of the collection under normal conditions is shown on an adjoining plan, 7) "Condensed Aisle" stack is also indicated. Since the cost of the "Aisle Compression Electric" is practically as much as building a new stack area, including standard stacks, it may be considered too costly. As an alternate, it is suggested that: a) The normal stack aisles could be reduced in width to 22", permitting one more row of ranges in the same space, b) That an additional high shelf be added (allowed for in ceiling height), (Will require new posts), c) That main aisles be narrowed by introducing one more 3*-0" section in each range, (This would prohibit use of the moving camera now in use in this area. Photo 7, page 32), The above is on the assumption this area would be chiefly for storage of books no longer in active usage. This last arrangement would result in an over-run of the assigned area in "CV level by about 11%, as indicated on the plan in Exhibit 21, It is believed this could be eliminated or reduced by closer shelving than 70% as might be practical with books, particularly serials already micro-filmed, such as those for use with the automatic storage and retrieval system. The cost savings of this method are indicated in the estimates. 2, Growth of Microfilm Storage As noted in Paragraph III-D-4-b-2), the new film vault will be filled to capacity by FY 1974, At that time the NLM proposed to extend the vault capacity for an additional five years by the use of off-site vault facilities for the security collection, with on-site vault storage of printing masters , 3• Graphic Image Storage and Retrieval System a. Specifications have been prepared for bidding for the installation of the first section of the Graphic Image Storage and Retrieval System, b. There are at least three systems now on the market - or developed - that will be able to meet the specifications with varying modifica- tions, Illustrations of two systems in use are shown in photographs 20 & 29 on pages 34 and 35, c. Basic Microforms, The NLM will create or obtain negative microimages of the Journal documents to be stored on 35mm roll film. The average document will consist of ten pages or less, d. Program, 1) Depending on the manufacturer, the frames may be retained in roll form, or converted into microfische on plastic base cards. Each journal article would fit on a card. It has been estimated that only 20% of the articles would need more than one card, 2) Space requirements for the systems under consideration would be approximately 190 sq.ft, to 250 sq.ft, per module containing the capacity to store 150,000 to 200,000 articles. It is estimated that the maximum number of modules required by 1974 would not exceed five (5), The total number of modules may be kept at five (5) indefinitely, if periodic discards are made. 3) Production methods. The final product of this system will be inexpensive hard copy prints on sheets 8-1/2" and 11", with provision for automatic production of an entire article. STANDARD STACKS AISLE COMPRESSION ELECTRIC CONDENSED AISLE C LEVEL C LEVEL C LEVEL 21 COMPACT STORAGE EXHIBIT 53 4) Viewing file items. It will be possible to retrieve, under the control of the operator view, frame by frame a file item at stations other than that used by the primary duplicating devices. These auxiliary stations may be located near the storage devices, away from the devices but in the same building, or at a remote location, 5) Remote copying. It will also be possible to generate enlargement prints of pages for items retrieved at certain auxiliary stations, 6) Installation. Requirements for installation of the device will include any special electrical, plumbing, and ventilation require- ments; and requirements as to humidity limits, acoustical treatment, floor loading, dimen- sions, floor space for device and operator, safeguards against fire hazards, etc, e. Existing Installation 1) Photo 20, page 34, shows an installation called a "Selectriever" which has a capacity of up to 200,000 documents which is in use in the Westinghouse plant in Buffalo handling their plan file, 2) Photo 21 shows an assemblage of available equipment at a station, or "console”, for use of students in the M.I.T, library, assembled in Project "Intrex". It presently has access to a block of engineering texts and permits direct interrogation with the University computer, 3) Photo 25, page 35, shows a punch tape data input machine for use with the M.I.T, University computer. 4) Photo 26 shows the automatic storage and retrieval system being developed in Project "Intrex" at M.I.T, A small digital computer operates this device which will connect with ten (10) consoles, 5) Photo 27 shows a working model of a console being especially designed for library use as part of Project "Intrex", It fits in a standard pedestal type desk, and will be readily adjustable to the physical requirements of different users. 4• Development of the Biomedical Communications Network Engineering & Communications Center) a. The selection of a network for improving the information and educational services within the medical community will be primarily based upon the present state-of-the-art in communication and computer sciences, b. Present communications technology makes it imperative that all communication modalities including satellites be considered as possible means of interconnection for Biomedical Communica- tion Network on a nationwide basis. A pilot project, RISC (Remote Information Systems Center) is already in operation in the NLM connecting the Library by wire with the more than ten remote computer systems around the United States. In the near future there will be TV, audio and video interconnections between sites which at a later date may utilize satellites via 25-30 foot antennae for transmitting and receiving purposes with ground connections to dedicated medical educational networks or to public ETV/ITV systems. This will permit more effective and less costly medical communications in support of specialized education. Ten foot (and smaller) antennae to allow direct satellite broadcasting to individual health centers, clinics and offices will probably be a still later phase of this project, TV, dial access telephone, commercial cables, etc, will also be used. c. The most highly developed example of an operating Network Center is the NASCOM installation at the Goddard Space Center in Greenbelt, Maryland, Although this installation is carried far beyond the relatively simple requirements of the LHNCBC, it does demonstrate the principles and methods involved. Photo 32, page 35, shows a part of the worldwide network control system, and Photo 33 the control desk for system management opera- tions within the Center itself, d. Specifications to meet the requirements of the LHNCBC are being developed. 54 Photo 25 shows the central control unit for the above classroom group. d. Photo 19 shows a mock-up of a dial access TV unit as part of the typical NLM carrell, e. A series of small rooms are planned adjacent to the main reading room. These would include: 1) 16m/m auto-load moving picture projector. 2) Several projection units in cubicles - Carousel, Audiscan, and 8m/m Fairchild (2) Mark IV single concept film projectors. 3) Room for working, repair of equipment, video tape recorders and storage. f. It is proposed to designate and arrange a portion of the main reading room adjacent to these special rooms as a TV area. 7, Audiovisual Production Facilities. NMAC. At this writing the NMAC will remain in Atlanta, Whether it combines with the LHNCBC, remains in its present location in the CDC complex in Atlanta, or relocates, it is faced with a large expansion program if it is to keep abreast of the demand for its services. This expansion is not part of this report. The overall program is detailed in Appendix II. Typical photographs of their activities are shown in Photos 13, 14, 15, page 33. C. Schematic Plans & Relationships 1. Linkage. Physical relationship of the new building to the old, (See cross-section on page 57, and model photos on page 35. a. To preserve the integrity of the design of the existing NLM, which has in itself become a symbol, and to create an individual identity for the LHNCBC,it is proposed to keep the two structures separated above grade. e. Tentatively, the Center would be located in the top of the LHNCBC building with direct connection to the antennae systems located in the roof structure. Provision would be made for the public to visit both areas in a practical manner. f. The type of space for the installation would be a ’’special purpose” space with a standard ’’pedestal” type raised floor with removable panels for ready access to wiring and cables in floor space, etc. to permit convenient installa- tion of new or additional equipment as system develops. 5. Communications Laboratory Facilities Adjacent to the Communications Center or directly below would be the small block of laboratory facilities. Through floor channels, ducts and conduits they would have direct connections to the Network Center. The general type of space occupied would be ’’Laboratory Space." At this time no detailed specifications of require- ments are available, 6. Audiovisual Equipment & Use The New Building will permit research and practice in the use of audiovisual equipment as an essential part of the overall program for the dissemination of biomedical knowledge. a. Not only may new equipment be tested and methods worked out for its effective use, but classes and seminars may be held demonstrating the use of the equipment at the same time realizing a ’’feed-back" on its effectiveness for this purpose, b. Since most of the equipment will be of the plug- in type it is assumed the space designated "Technical" will meet the requirements. c. For educational and classroom work an example of an existing instructional unit of three class- rooms with one central projection room as shown in Photo 26, page 34. This uses rear view projectors as well as TV screens and cameras. It includes a system for audience participation. 22 LHNCBC SITE PLAN TERRACE LEVEL EXHIBIT 23 LHNCBC A LEVEL (LINK) EXHIBIT B and C LEVELS 24 LHNCBC - SECTION - TOWER EXHIBIT 58 b. To permit the two units to function efficiently as one overall unit of the NLM, the three levels below grade "A”, ,rBM, & ”CM would be continuous. The major points of these connecting levels are as follows; 1) Terrace Level, (See Exhibit 22, page 55 and Photo 34, page 35,) The new construction below grade would form a sort of podium providing a setting for the new LHNCBC building. The roof of this podium - over "A” Level - would form an out- door Terrace connecting the two buildings. While not the principal connection, a door from the main Reading Room of the NLM to the Terrace would permit access to the Terrace for use in pleasant weather for recreation or crossing over to the LHNCBC as well as, incidentally, to the parking space. The main entrance to the LHNCBC would be at the Terrace level as shown. To emphasize the vehicular approach and provide turning space, 15 car spaces would be sacrificed in the south end of the existing parking space. These would be regained in a new 85 car parking space to the west of the proposed LHNCBC, a net gain of 70 parking spaces. 2) "A" Level. (See Exhibit 23, page 56). a) This is the principal communicating level for personnel & visitors. It will be noticed a continuous passage is indicated leading from the stairs or elevator at the main entrance of the NLM to the vertical circulation system of the LHNCBC. It also connects to the new auditorium on this level, facilitating joint use. The Billings Auditorium, equally accessible from the passage, in the old building, will be remodeled for smaller groups. b) For the interest of visitors, particularly those on tours of the building, along the passage in the NLM Building will be view windows into the activities of the Graphic Image Storage & Retrieval section and the RSD Photo duplication section. c) Activities of the Bibliographic Services Division located on this level in the NLM will be conveniently connected to the Reference & Catalog services above on the main floor by a principal stair. BSD Indexers and MEDLARS facilities will maintain continuity of space into the new structure and be located in close relation- ship to the OCES Input Unit as shown, d) The OCES Computer Room is tentatively located on this level in the S.W, corner in principle because it will be used by both the activities of the NLM and the LHNCBC, The corner location permits its future expansion with continuous space. 3) MB,f Level, See Exhibit 24, page 57, a) "B" Level is principally a stack level in the NLM and will so be continued in the new structure. In both buildings the location is contiguous to the area under the existing parking space designated originally, and reserved for a future major expansion of the stacks. b) Additional truck loading and receiving space will be provided on this level for the complex, 4) "C" Level, See Exhibit 24, page 57, As indicated, "C" Level maintains similar continuity of stacks as the level above. 2• New Building a. Ground Floor. (Terrace Level) 1) The entrance to the building is from the Terrace on the north side, (Model Photo 36, page 35). 2) Parking spaces are in close proximity, 3) In going through to the elevator core the visitor will pass through exhibition areas on either side of the foyer. 59 4) On the far side of the lobby would be con- ference rooms - most convenient to visitors for the day coming to meetings from outside. Between sessions there would be ready access to the landscaped terrace. 5) One flight down on "A" level would be the main Auditorium - again located primarily for convenience of visitors. 6) As previously noted there would be all-weather access to the NLM on ”AIT level and also from the Terrace to the reading room. 7) This Terrace, incidentally, would be a good location for a work by a talented artist. It is believed that 1% of the cost of a public building may be spent on such enhance- ment . b. Above Grade. Exhibit 24, page 57. Shows a typical floor plan divided into a pair of work areas either side of the elevator core. These areas may be subdivided in accordance with the requirements of the particular department and changed in the future in the manner of a conventional office building. c. Sections. Exhibit 24, The cross section shows how the space may be allocated in the Center, recognizing it primarily as a communications & technical facility; 1) Roof. Roof top antennae of various types screened by non-magnetic construction for protection from weather and permit design symbol of the LHNCBC against the sky. It will be designed for access to visitors, 2) Upper floors. As the principal "tenants" as well as for technical reasons related to the communications network, the LHNCBC itself is located on the upper floors. 3) Middle floors. The SIS & OCES are located next below the LHNCBC as being the most closely related divisions in their functioning. 4) Lower Floors. The EMP is indicated here as having no close ties with other departments. The additional space required for the LO, including Network Training, is indicated just above the ground floor as being nearest to the conference rooms as well as closer to the Main Library. 3• Rehabilitation of NLM Changes as indicated on diagrammatic plans for 1974, (Exhibits 15A through 19A, pages 41, 43, 45, 47 & 49) D, Approach to Design of New Structure 1• Location on Site a. With reference to the site model of existing condition (Photo 3, page 32) it will be seen there is; 1) a small area available to the right rear of the building (NW), 2) the parking space directly behind the building (W) but reserved for future stack expansion, 3) a fairly large area to the south west. (The "Greenbelt" runs across the front of the building and round the south side of the N.I.H. reservation - more or less across the brook). b. The base section of the new building covers approximately 35,000 sq.ft. This last area to the southwest is the only place large enough for the new project on the NLM site. c. The site for the building has several advantages: 1) Access by the road west of parking space permits it to have own entrance. 2) Sloping site down to brook on south permits ready access to building at more than one level, as well as permitting windows to south. Presently convenient for Service Entrance, (Photo 35, page 35). 60 3) Overall project lends itself to visual relationship with the new Fogarty Inter- national Center in facing it across the open parking space and own unoccupied area beyond. 4) By taking part of south end of parking space, a dignified and convenient "off-streetM entrance plaza and turn around becomes possible. (Model Photo 35, page 35). 2. General Shape & Design Characteristics a. The reasons for the large lower levels below grade tied in with the "AM, "B!l, & "CM levels of the NLM have already been given. Together they form a base structure or "podium" for the tower with its top designed as an effective terrace. This Terrace will be useful as a gathering place between seminars and lectures, for outdoor reading and for recreational purposes, b. From previous studies (Feasibility I) of a building of different heights, it had been con- cluded and accepted that a tower form would be most useful to the LHNCBC purposes and would also permit an expression of it as a unique communication center. The antennae platform could be designed to create an identifying symbol and at the same time act as a line of sight & weather screen to the antenna equipment. This equipment could be expected to change its shape at relatively frequent intervals as technical developments take place, and this might change the appearance of the top of the building unless so screened. c. The vertical strips in limestone recall the scale and major divisions of the NLM between its narrow windows. The limestone itself will be treated with the same pattern in the stone- work as the NLM, These would provide certain unifying elements, 3. Future Expansion a. The present tower is thought of as creating the permanent image as seen from Wisconsin Avenue (Model Photo 34, page 35). It is designed to be expanded by a duplication of space on the west side (Model Photo 36, page 35). This would increase the importance of the north elevation which is the entrance side and which faces the Fogarty International Center. b, The above area of future expansion would now be used effectively for parking, c, The base, of course, would expand in the same direction as the tower, desirable for the exten- sion of the computer space and the mechanical space. Additional expansion of the base to the south would also be practical. Interior parking might then become necessary at lower levels. d, The stack expansion for the NLM reserved under the parking space has already been noted. V. CONSTRUCTION & COST A. Outline Specifications For the purpose of establishing the budget, it will be assumed that the following items are included: 1. Site Development (See Site Plan Exhibit 22, page 55.) a. Grading and drainage. b. Roads, walks, new turnaround at building entrance, etc. c. Granite curbs, steps, terrace paving, etc. d. Exterior lighting. e. Planting and seeding. f. 85-car paved surface parking area, 2, Utilities (See NLM Site Plan Exhibit 4, page 18). Conclusions on the extension of utilities on the part of the N.I.H. are not firm at this writing. The following assumptions, therefore, have been made for estimating purposes as an allowance. They will be subject to review by the Engineering Design Branch, Division of Research Services, N.I.H., for later establishment of actual scope of work. a. Cold Water Supply 8" cold water main will be connected to existing service line to NLM building. 61 b. Sanitary System 10” sanitary sewer will be run from new building to existing manhole near Wisconsin Avenue serving the present 8” line from NLM building. c. Storm Water Drainage Storm water drainage will be run to present brook in similar way to the NLM building. d. Steam Steam and pumped return service lines will be taken from existing Manhole CS-49. New 8” steam, and 4" Pumped Return will be run for a distance of 6601 to new manhole, from which point 6” steam, 3" Pumped Return and 1-1/4" drip will be run to new building. e. Chilled Water Chilled water service will be connected to existing 20" lines at Manhole CS-49, New lines will be 18" from existing Manhole CS-49 to new Manhole about 400* from new building. From new manhole, lines will be 14" to new building, f. Electrical Electrical light and power service will be connected to present feeders serving NLM. g. Communications Communication cables (telephone, Supervisory, Fire Alarm, Watchmans* Report Systems) will be run to Manhole T-3 Dwg. 9-41 Project No. 18096. Extension of these cables to final terminal points will be done as determined by N.I.H, h. Not provided for in budget estimate 1) Possible future tie-in with pneumatic tube communications network. 2) Extensions of communications cables beyond Manhole T-3, 3) Any assessment for increase in boiler and refrigeration plant capacity. 3, Rehabilitation of Existing NLM Building (See Exhibits 15 through 19, ISA through 19A, pages 40 through 49) . a. Construction and finishes to conform to standards in existing building and to tie in with adjacent areas. b. Alteration to existing mechanical and electrical systems as required for new space allocations and functions in the existing building. 4• General Construction of New Building a. Foundation and Structural Framing 1) Reinforced concrete footings and foundation walls. 2) Foundation drainage. 3) Base structure - reinforced concrete, flat slab construction commensurate with levels "A", "B" & "C" of contiguous NLM building. 4) Structural steel framing with masonry fire- proofing . b. Floor and Roof Construction 1) MC" level floor - Concrete slab on fill, reinforced. 2) Other floors and roof - Reinforced concrete slab. Depressed slab in computer and certain adjoining areas. (Alternate for tower floors - steel cellular floor decks in place of con- crete with encased underfloor duct systems). 3) Live load on typical floor 80 and 100 lbs,/sq.ft, as required. Live load on "A”, "B", & "C" level 125 lbs./sq.ft, c. Exterior Wall Construction and Finishes 1) Walls below grade - Reinforced concrete with membrane waterproofing and protection. 2) Solid walls above grade - masonry wall with cut limestone exterior facing; plaster over furring on inside. 62 3) Window wall - ’’Institutional" grade metal, or precast concrete system. Heat reducing glass. d. Roofing 1) 4-ply built up roofing. Granite paving over terrace roof. Traffic top on tower roof. 2) 1-1/2” rigid insulation, e. Interior Walls and Partitions 1) Masonry block walls around stairs, elevators, toilet rooms, auditorium, computer room, and other special purpose areas, 2) Prefabricated dry-wall office partitions for offices, storage, etc. f. Interior Finishes 1) Vinyl-asbestos floor tile in general office and technical space. Terrazzo and carpet in certain public areas. 2) Walls painted in general. Special treatment and/or high grade finishes in certain public areas such as lobby, auditorium, etc. 3) Natural finished wood doors in general except where metal doors are required by code. 4) Acoustical ceiling in general, 5) Appropriate finishes in toilet rooms and other service areas, g. Plumbing 1) Complete plumbing system, including fixtures, accessories, soil, waste, and vent lines, hot and cold water supply, etc, 2) Roof drains, leaders, and connection to storm water drainage system, 3) Fire protection system including standpipes - from separate exterior fire protection main. Fire extinguishers as required. h. Heating, Ventilating and Air Conditioning 1) New chilled water service from existing underground chilled water system, 2) Steam and pumped return from existing under- ground piping system. 3) Heating system - Forced hot water system zoned for exposure. Modular arrangement of heating and air conditioning system to afford individual temperature control of offices. 4) Entire building air conditioned. Air handling units to be selected and arranged to serve spaces separately such as auditorium, computer areas, office spaces, etc, i. Electrical 1) Complete electrical distribution system for light and power requirements including sub- station, switchgear, conduits, cables, boxes, etc. 2) Complete lighting and power system including fixtures, convenience outlets, power outlet for motors, equipment, etc. 3) Emergency lighting system, 4) Fire alarm system connected to central system. 5) Clock system. 6) Telephone system. 7) Intercommunication system. 8) Underfloor duct system throughout office areas for complete flexibility, 9) Emergency generator for communications equipment. 63 B. Cost Estimates 1• New Building a. General construction $8,550,000 b. Site Development Roads, surface drainage, lighting, new parking, walks, grading, trees, and planting. 208,000 c. Utilities (on site) 432,000 d. Bookstacks 100,000 e. Work of Artists - 1% 85,000 Sub-Total $9,375,000 Contingencies - 5% 469,000 TOTAL $9,844,000 2. Existing Building - Rehabilitation a. Alterations $ 628,000 be Compact Bookstacks (Basic Scheme) 598,000 Sub-Total $1,226,000 Contingencies (Alterations) - 10% 63,000 " (Bookstacks) - 5% 30,000 TOTAL $1,319,000 Alternate: Substitute Condensed Aisle bookstack arrangement for Compact (Basic Scheme) DEDUCT $433,000. See Exhibit 21, page 52. 3• Summary a. New Building $9,344,000 b. Existing Building - Rehabilitation $1,319,000 TOTAL $11,163,000 4. General Notes (Applicable to all above estimates) a. Costs estimated as of July 1969. For each yearly increment to bidding date plus one year thereafter, ADD 9,5% per year. Under present conditions, forecasting the rate of inflation is very uncertain. However, this rate averages the forecasts of three authoritative sources for the year 1969, based upon recent experience. b. "Building1’ cost limited to 5 feet outside building. Work beyond 5* in "site development" and "utilities". c. Included: Rock excavation, and an allowance of $100,000 for fallout protection, d. Excluded; 1) Equipment other than bookstacks - e.g., case- work, movable furniture and equipment, tape files, film equipment, etc. 2) Computer and console wiring. 3) Utility work beyond points of connection described above, pages 60 and 61, Scope of the extension of utilities and thus the cost of supporting utilities is not firm as of submission of this report and is subject to verification by Engineering Design Branch, Division of Research Services, N<,I0H0 4) Pneumatic tube facilities, 5) G.S.A, Supervision and administrative costs, 6) Design costs. e. Costs of rehabilitation of existing building estimated as of July 1969. Cost projection to relate to construction schedule, page 64, C, Schedule See Exhibit 25, DESIGN AND CONSTRUCTION PROGRESS SCHEDULE 25 PROGRESS SCHEDULE EXHIBIT APPENDIX I 1974 Nil EXPANSION PROGRAM IN BETHESDa PROPOSED MT LHNCBC BUILDING and REHABILITATION OF EXISTING NIM BUILDING Pages 1-1 to 1-22 I. OFFICE OF THE DIRECTOR 19 6 9 1 9 7 4 GSA HEW MAIN BLDG 1974 LHNCBC BLDG 1974 REMARKS ROOM STA P AREA SUBTOTAL STA P AREA SUBTOTAL GUIDE 0 T L C Sp s P AREA SUBTOTAL F AREA SUBTOTAL A* Office of The Director 1* Director M142 1 1 410 1 1 410 0 1 410 2. Deputy Director M144 1 1 320 1 1 320 0 1 320 3. Spec* Asets, to Director M119 M136 M139A C24 4 4 220 180 310 170 4 4 800 200 0 2 190 240 2 400 4. Secretaries-Receptionists M101 M112 5 4 600 200 5 5 600/ 100 0 5 500 5. Program Planning 2 2 300 150 0 2 310 6* Board Room M150 1160 1160 Sp 1160 10 3470 13 3590 11 si'STo 2 400 B. Office of Admin. Management 1 1 1. Executive Officer M109 1 1 230 1 1 200 200 0 1 230 2. Asst. Exec. Officer Ml 10 1 1 160 1 1 200 200 0 1 160 3. Financial Management MIC 5 M108 3 3 420 3 3 350 150 100 0 3 420 4. Contract Officer 11104 1 1 100 4 4 450 100-3 150-1 0 4 450 5. Personnel M106 M107 3 3 430 6 5 660 100-2 150-3 0 5 650 6. Management Analysis M113 1 1 170 2 2 260 100 150 0 2 250 7. Training Officer C22 1 1 170 1 1 100 100 0 1 100 8. Budget Analysts 3 3 450 100 160 0 3 300 A 9. Purchasing Agents 3 3 300 100 0 3 300 10. Secretary & Clerical M102 11 7 1100 9 9 900 70 100 0 8 800 1 100 11. Supply Office, Clerical C28 7 7 900 9 9 900 70 100 0 9 900 12. Duplicating C30 2 2 420 2 2 1620 70 0 2 1620 13. Storage-Supplies, Exhibits & Equipment C29 3160 11160 s 11160 19 6 9 19 7 4 GSA HEW MAIN BLDG 1974 LBNCBC BLDG 1974 REMARKS ROOM STA P AREA SUBTOTAL STA P AREA SUBTOTAL GUIDE 0 T L C Sp s P AREA SUBTOTAL P AREA SUBTOTAL 14• Mail Room A 55 4 4 510 6 6 910 70 0 5 510 3 400 15* Shipping & Receiving A36 1 1 800 1 1 800 0 1 800 420 16. C-Level Stack Storage 860 s 52 9ii0 To~ 9 CM o> HI 25 3870 25 13700 C. Office of Public Information- Publications Management 1* Chief M122 1 1 220 1 i 200 200 0 1 180 2* Deputy Chief ' M120 1 0 170 1 1 150 150 0 1 180 3* Seoretarial,Cler*,& Reoep* M112 6 4 820 5 5 500 70 100 0 5) ) 1) 4* Writer 1 1 150 150 0 880 5* Exhibits Director 1 1 510 1 1 550 0 1 530 6* Storage 470 S 6 2l90 1553— 8 iMb £55 D* Common Space 1* Conference Room B M131 760 760 C 760 2* Conference Room C C 220 0 5* Billings Audit* & Study A43 2500 2500 Sp 2500 4* Auditorium (Nesr) 4500 Sp 4500 5* Conference Room A 139A 320 C 320 6* Lunch Room A19 2740 2740 Sp 2740 0 6220 " 10820 “ 0 6320 0 4506 TOTAL - I - OD 48 21310 72 35180 44 14560 28 21130 • II. COMPUTER & ENGINEERING SERVICES 1 9 6 9 1 9 7 4 GSA HEW MA .IN BLC >G 1974 LHNC ;bc bii )G 1974 REMARKS ROOM STA P AREA SUBTOTAL STA P AREA SUBTOTAL GUIDE 0 T L C Sp s P AREA SUBTOTAL P AREA SUBTOTAL A. Office of -tiie Chief 1. Immediate Office a. Chief 0556 1 1 220 1 1 300 300 0 1 300 b# Deputy Chief C40 1 1 220 1 1 200 200 0 1 200 o* Special Assistant C39 1 1 (220 ) ( 140s 1 1 100 100 0 1 100 d. Secretaries C39 CSSs 1 2 800 2 2 160 760 90 70 0 2 160 760 2. Project Mgrat. Staff a. Chief C36 1 1 220 1 1 200 200 0 1 200 - b. Analysts 1 2 2 250 150 100 0 2 250 o* Contractor 1 0 100 0 0 100 d. Secretary CSSs 1 140s 360 1 1 70 620 70 0 1 70 620 3. Conference Room C34 440 440 500 500 c 600 600 (T“ 1660 “T~ 1880 "7“ ~rm B. Systems Devlpnfc* Section !• Section Head a. Chief 035 220 1 1 200 200 0 1 200 b* Deputy Chief 1 1 200 200 0 1 200 c« Secretary CSSs I 140s 360 1 I 70 470 70 0 1 70 470 2. Support Software Unit a* Chief CSSs 1 140s 1 1 200 200 0 1 200 b. Analyst/Programmers CSSs 3 420s 5 5 500 100 0 5 500 o. Contractor CSSs 2 280s 8 0 760 0 0 760 d« Secretary 840 1 1 70 1530 70 0 1 70 1530 1 9 6 9 1 9 7 4 GSA HBKT MAIN BLDG 1974 LHNCBC BLDG 1974 REMARKS ROOM STA P AREA SUBTOTAL STA P AREA SUBTOTAL GUIDE 0 T L C Sp S P AREA SUBTOTAL P AREA SUBTOTAL 3. Data Mgmt* Systems Unit a* Chief C33s 1 140s 1 1 200 200 0 1 200 b* Analyst/Programmers C33s 2 280s 5 5 500 100 0 5 500 c* Contractor CSSs 3 420s 5 0 490 0 0 490 d* Secretary 840 1 1 70 1260 70 0 1 70 1260 8 2040 So Tt“ $260 17 3260 Processing Support Section !• Section Head a* Chief 134 1 1 180 1 i 200 200 0 1 200 b. Deputy Chief 133 1 1 (170 ( ( 1 i 160 150 0 1 160 c« Secretary 133 1 1 350 1 i 70 420 70 0 1 70 420 2« Production Control Unit a. Supervisor (Chief) 132 1 1 ( ( (210 ( ( 1 i 150 150 0 1 150 b* Dist* Control Clerk 132 1 1 1 i 90 90 0 1 90 o* Tape Librarian 132 1 1 1 i 100 100 0 1 100 d# Administrators 2 2 200 100 0 2 200 e« Contractors 2 0 200 0 a 200 f* Secretary 210 1 1 70 810 70 0 i 70 810 3* Input Unit a. Unit Head 143 1 140 1 1 100 100 0 i 100 b# EAM Area 1 1 90 90 T i 90 c* Input Typing & Proof- reading 140 142 19 14 1750 15 15 1050 70 T 16 1060 dm Contractors 152 640 2530 8 0 660 1800 T , 0 560 1800 1 9 6 9 1 9 7 4 6SA HEW MAIN BLDG 1974 LHNCBC BLDG 1974 REMARKS ROOM STA P AREA SUBTOTAL STA P AREA SUBTOTAL GUIDE 0 T L C Sp S P ARTCA SUBTOTAL P AREA SUBTOTAL 4* Computer Operations Unit a* Unit Head 1 1 1 150 150 0 1 150 b. Supervisor 1 1 150 150 0 1 150 c. Computer Room 140 7 7 1640 5180 T 5180 d« Maintenance Room 135 3 440 T e* Tape Storage 137 310 0 f. Mechanical 136 400 2790 5480 T 6480 32 5880 8510 28 8510 Systems Application Section 1* Section Head a* Chief C37 1 1 220 1 1 200 200 0 1 200 b* Deputy Chief 1 1 200 200 0 1 200 c* Secretary C33ft 1 140fl 1 1 70 70 0 1 70 2* Data Base Unit a* Chief C33s 1 140s 1 1 200 200 0 1 200 b* Secretary 1 1 70 70 0 1 70 c« Programmers/Analysts C33s 5 420s 3 5 300 100 0 3 300 d« Contractors 333s 4 560s 1120 3 0 280 850 0 0 280 850 3* Retrieval & Users Product Unit a« Chief 1 1 200 200 0 1 200 b« Seoretaxy 1 1 70 70 0 1 70 c. Programmer/Analysts C33s 4 560s 6 6 580 100 90 0 6 580 d. Contractors 2 280s 3 0 290 0 0 290 e* ACM 840 1 1 200 1340 200 0 1 200 1340 4. NMAC-Contractors CSSs 4 560s 560 2 0 190 190 0 0 190 190 10 2880 TT" 2850 17 2850 Total - II OCES 56 12,400 71 16,500 . 71 16,500 1 9 6 9 1 9 7 4 GSA MAIN BIDG. 1974 LHNCBC BLDG. 1974 Hew loom Sta P Area Subtotal Sta P Area Subtotal Guide 0 T L c Sp s P Area Subtotal P Area Subtotal REMARKS III. associate director for LIBRARY OPERATIONS A. Office of Associate Director 1. Immediate Office a. Associate Director T1116 1 1 270 1 1 300 300 0 1 270 b. Deputy Associate Director M118 1 1 210 1 1 200 200 0 1 210 c. Secretaries to a.b* Ml 17 2 2 160 2 2 200 100 0 2 160 d. Adm. Officer Ml 14 1 1 160 1 1 150 150 0 1 150 e. Adm. Assistant 1 1 ) ) 170 100 0 i) ) 200 f. Secretary to d. 1 1 ) 70 0 i) g. Special Assistants M120 2 2 170 960 1 1 150 1,170 150 0 1 170 1,160 2* Library Network Management &• Head - Network Staff 1 1 200 200 0 1 220 b. Professionals 10 10 1500 150 0 10 1640 c. Secretary to a* 1 1 ) ) 420 70 0 i) ) 720 d. Clerical Support 5 5 ) 2,120 70 0 5 ) 2,580 3« Library Network Training a* Head 1 1 200 200 0 1 200 b. Deputy 1 1 200 200 0 1 200 o. Professional* (5 offices) 4 4 400 100 0 4 400 d. Clerical Support 3 3 210 1,010 70 0 3 210 1,010 7 960 4,300 26 3,740 9 1,010 B. Technical Service Division 1* Office of Chief a. Chief, TSD 125 1 1 280 1 1 500 300 0 1 280 b. Deputy Chief 122 1 1 160 1 1 ,200 200 0 1 160 c. Secretary 121s 1 i ) ) 250 2 2 140 70 0 2 ) ) 350 d. Assistant; 124* 1 i ) 1 1 150 150 0 1 ) e. Special Assistants 125 1 124 2 2 320 3 3 450 150 0 3 480 6 1,010 8 1,240 8 1,070 19 6 9 1 9 7 4 GSA MAIN BLDG. 1974 LHNCNC BLDG. 1974 REMARKS BE?/ Room Sta P Area Subtotal Sta P Area Subtotal Guide 0 T L C Sp S P Area Subtotal P Area Subtotal 2. National Catalog Program a* Head 127 1 1 160 1 1 200 200 0 1 150 b. Asst. Network Mgmt. 1 1 150 150 0 1 130 o. Secretary 126s 1 1 430 1 1 90 90 0 X ) ) 2 ) d. Training Officers 130 2 2 250 100 160 0 ) ) 2 ) ) 2 ) ) 1 ) ) e« Coordinators 1 X ) ) 1) ) ) ) 2 2 200 100 0 f. Editors 1 2 2 300 150 0 g. Asst. - Cataloging 1 1 160 150 0 1700 h. Secretary ) 2670 1 1 90 90 0 1 ) ) ) 2950 130 sf/person allowed 150 i. Catalogers 1 X ) ) 4 4 520 90 0 4 ) ) j. Senior Catalogers 11 XX ) ) X ) ) 8 ) 14 14 2100 100 0 14 ) ) 2 ) ) 8 ) k. File Maintenance 1 2 2 180 90 0 1. File Clerks 8 3,280 8 8 660 4,790 70 0 4,930 3« Serial Data Program a« Head 1 1 200 200 0 X ) ) X ) ) 2 ) ) 2 ) ) X6 ) ) 4 ) ) b. Editor 1 1 160 150 0 c. Catalogers 2 2 260 100 0 130 sf/person allowed d. Back Issues 2 2 180 90 0 e. Checkers & Searchers 13 X3 ) ) ) ) 16 16 1350 90 0 4900 f. Clerical 4 4 280 2,420 70 0 4,900 4« Selection/Acquisition ) ) a. Head 1 X ) ) ) 2390 1 1 200 200 0 X ) ) X ) b. Deputy 1 1 150 150 0 ) ) o. Secretary 1 X ) ) 6 ) 1 1 90 90 0 X ) ) 9 ) d. Area Specialists 6 9 9 1360 100 0 160 sf/person allowed e. Assts.-Exchange,Fiscal,Clai n 1 X ) 3 3 270 90 0 3 ) f• Clerical 4 4 ) 6 6 420 70 0 6 ) 2,390 2,480 6* TSD Stacks 6,140 6,140 6,140 67 12,820 93 17,070 93 17,040 19 6 9 1 9 7 4 GSA MAIN BLDG. 1974 LHNCBC BLDG. 1974 REMARKS HEW Room Sta P Area Subtotal Sta P Area Subtob al Guide 0 T L C Sp s P Area Subtotal P Area Subtotal C. Reference Service Division 1* Office of the Chief a* Chief, RS 162 1 1 290 1 1 200 200 0 1 290 b. Deputy Chief 160 1 1 190 1 1 160 160 0 1 190 c. Secretaries 161 2 2 160 2 2 140 70 0 2 160 d« Special Assistants 640 2 2 200 690 100 0 2 200 840 With Reference Section 2* Reference Section a* Head 164 1 1 220 1 1 160 150 0 1 ) ) 10 ) ) 6 ) ) 2 ) b. Librarians ( ( ( ( ( 8 7 •) ) 6 ) ) 1 ) 10 10 1200 100 0 2,620 2 Librarians Station o* Technicians 153 6 2400 6 6 780 90 0 in Reading Room at 160 sf A>erson d. Clerical 1 2 2 140 70 0 130 sf/person 2,620 2,270 3, Loan and Stack Section a* Head A61a 1 1 ) 1 1 160 160 0 1 210 ) 300 b. Assistant Bead A61a 1 1 ) 1 1 100 100 0 1 ) ) 2 ) ) 6 ) ) 27 ) o. Secretaries 1 1 ) ) M 1 2 70 70 0 1200 2 shifts d. Searchers A61 3 1200 3 5 270 90 0 e. Pages In stacks 15 ) IS ) 14 27 980 70 0 1,500 1,670 1,410 4* Photoduplioation Section a« Head A50a 1 210 1 200 160 0 X) b« Assistant Head A50 1 - 1 - 100 0 1) ) 1 2) ) ) o* Mechanic A50 1 - - 100 r d. Photo Technicians 2 - 100 T e* Microfilm Camera Room A22 2 490 T f* Quality Control Room A22a 2 420 L ) ) g. Photo Lab - Dark Room A53 1 330 18* 8500 L is) : .0230 h. Copy - Camera Room A52 A41 1 270 T j i* Photostat & Copyflo A50 s 5 2350 L > j# Graphic Image System 2000 T ) ) >" k. NBS Room A60b 1 - 210 200 0 !• Clerks A 50 s 1 1 3 3 0 si 4,290 10,900 87 10,250 00 1 H 19 6 9 1 S 7 4 QSA: MAIN BIDG. 1974 LHNCBC BLDG. 1974 REMARKS HSff Room Sta P Area Subtotal Sta P Area Subtot al Guide 0 T L C Sp s P Area Subtotal P Area Subtotal 5* Preservation Section a. Supervisor C27 1 1 200 1 1 150 160 0 1 200 b* Secretary & Assistant 2 2 160 70 2 ) 90 0 ) ) ui c. Bindery C26 9 ) 11 2820 70 T 11 « 120 sfB1320 sf / ) 2960 3890 1500 sf stg.«2820 sf d. Mlororeoords C26 3 ) 11 1320 70 T U) 11 ® 120 . 1320 sf e. Film Vault Service Area CIS 2 2 360 2 2 350 70 Sp 2 560 f. Film Vault C16 920 920 Sp 920 4,430 6,720 5,360 6« Mid-Atlantic Reg. Library 7 7 910 0 7 1060 1,060 7 @ 130 69 13,470 121 22,060 121 21,510 D. Bibliographic Services Division 1* Office of Chief a. Chief A50a 1 1 230 1 1 200 200 0 1 220 b. Deputy Chief ASOb 1 i) ) 210 1 1 150 150 0 1 170 o. Special Assistants ASOb 1 i) 2 2 300 150 0 2 140 150 d. Secretary & Assistant A50c 2 2 190 630 2 2 180 830 90 0 2 aso 930 2. Quality Control Staff i) ) a* Head A50 1 280 1 1 150 160 0 1 220 b. Information Specialist A50 3 3) 6 6 500 100 0 6 ) ) 1100 o* Clerical 4 4 280 70 0 4 ) 280 930 1,320 3* Index Section a* Head AS 8b 1 1 180 1 1 200 200 0 1 200 b. Training A58& A58c 1 X 2 180 180 1 1 160 150 0 1 160 c. Senior Indexers A58 4 2) ) 16) ) 8 8 1040 100 0 8 1040 8 130 sf d. Indexers ASS,5 9,60 16 2760 18 18 1800 100 0 18 1800 e* Trainees ASS 16 ! 210 210 18 - 1260 70 0 1260 f. Clerical A50 6 6) 150 3,870 9 9 630 5,080 70 0 9 630 6,080 19 6 9 19 7 4 6SA main bldg. 1974 LHNCBC BIDG. 1974 REMARKS HEW Room Sta P Area Subtotal Sta P. Area Subtotal Guide 0 T L C Sp s p Area Subtotal P Area Subtotal 4* Medlars Management Section a* Head 146 1 1 140 1 1 200 200 0 1 200 b. System Analysts,Searchers 152 6 6 ) 16 16 2240 100 16 2240 16 • 140 sf• average ) 150 0 o* Trainees 152 10 ) 12 - 1560 70 0 12 1560 12 ® 130 sf/p d. Coordinators 162 1 ) 1 ) \ 2040 3 3 300 100 0 3 300 e. Clerical 1 ) X ) 4 4 280 70 0 4 280 2,180 , 4,580 4,580 5* Mesh Section a* Head 145 1 1 140 1 1 200 200 0 1 200 b. Sr. Mesh Officer 144 1 1) 1 1 150 150 0 1 150 o. Mesh Specialists 144 3 / 3 ) 10 10 1500 150 0 8 1290 2 300 ) 710 d. Editors 144 1 i) 2 2 200 100 0 2 200 e. Clerical 144 1 ) i ) 3 3 210 70 0 3 300 850 2,260 1,590 850 6. Search Section a. Head A21 1 1 ) 1 1 150 150 0 1 170 ) 210 b. Secretary A21 1 i ) 1 1 70 70 0 1 ) ) c. .assistant A20 1 1 ) 1 1 100 100 0 1) 700 J 460 ) d. Searchers A20 5 5 ) 5 6 500 100 0 5 ) 670 820 870 — 7* Conference -Room-Training 550 550 C 61 8,150 102 15,050 35 4,710 67 10,510 1 9 6 £ 1 9 7 4 GSA MAIN BLDG. 1974 LHNCBC BLDG. 19 74 REMARKS HEW Room Sta P Area Subtotal Sta P Area Subtotal Guide 0 T L C 3P S P Area Subtotal P Area Subtotal E. HISTCHy OF MEDICINE DIVISION 1. Office of Chief a* Chief 109 1 1 270 1 1 200 200 0 1 270 b. Secretary 108a 1 1 160 1 1 100 100 0 1 160 c. Curator - Early Manusc*pt« 116 130 1 1 150 150 0 1 130 560 450 560 2* Cataloging a* Historian 116 117 1 100 90 1 1 160 160 0 1 100 b. Catalogers 118 2 70 3 3 300 100 0 2 160 c. Library Technician 112 i) ) 660 1 1 ) ) 650 70 0 i) i) 650 d. Clerical 112 2 ) 910 2 2 ) 1,100 70 0 2 ) 910 3* Reference and ILL a* Sr, Ref. Librarian 1 1 150 150 100 0 1 b. Ref. Lib. & Secy. (Desk) 108 2 460 2 2 450 70 0 2 450 At Desk c, ill. Lib* Technician 2 2 140 70 0 2 200 In Stack d. Office Machine Operator C14 1 180 1 1 180 0 1 180 630 920 830 4* Oral History Group a* Deputy Chief A2 1 1 170 1 1 200 200 0 1 170 b. Secretary A6s 1 1 100 1 1 100 100 0 1 100 o. Assistant Historian - 2 2 200 100 0 2 200 d. Clerk-Typist - 270 1 1 70 670 70 0 1 100 570 6. Archives a* Archivist A6 1 1 110 1 1 100 100 0 1 110 b. Assistant - - 1 1 100 100 0 1 60 o. Clerk-Typist A1 ? 1 1 _ 1 1 70 70 0 1 110 270 170 Hoorn Sta 19 6 P 9 Area Subtotal Sta. 1 9 1 P. r 4 Area Subtotal GSA Em Guide 0 T L C Sp s Ma3 P CN BLD Area G. 1974 Subtotal LHN P CBC BL Area DG. 1974 Subtotal R3&IARKS 6. Bibliography a. Historian 1 1 160 160 0 1 170 b. Librarian A3 1 1 170 1 1 130 100 0 1 170 • o* Clerk-!fypist A6s 1 1 100 270 1 1 70 350 70 0 1 60 400 7. Prints a* Curator - 1 1 160 150 0 1 130 b. .art Stack A1 2 1 GOO 880 2 2 880 1,030 0 2 880 1,010 * . 8. Reading Room 3450 3450 Sp 3450 Studies 140 140 0 140 Incunabula 380 3,970 380 3,970 Sp 380 3,970 18 7,600 8,660 30 8,420 F. SPECIAL HJRPOSB,SPACES 1* Stacks 74800 106540 82240 24100 2* Catalog 4270 4270 4270 3« Reading Room 12200 12200 i i 12200 4* A.V* Reading — 5000 1 \ | 2940 5« Studies 1750 2830 » i 2150 93,020 130,640 103,800 24,100 TOTALS - III - lo 212 136,020 380 197,710 304 159,220 76 36,620 Room Sta 19 6 P 9 Area Subtotal Sta 1 9 * 7 4 Area Subtotal GSA HEW Guide 0 T L c Sp s MAIN P BLDG. Area 1974 Subtotal LHNC P BC BID Area G. 1974 Subtotal REMARKS IV. EXTRAMURAL PROGRAMS A. Office of the Assoc. Direct©: • 1. Immediate Office a* Associate Director 1 1 200 1 1 300 500 0 1 300 b. Assistant Director - - - 1 1 300 300 0 1 300 o. Special Assistant for Program Plan 1 1 185 1 1 200 200 0 1 200 d. Research Analyst - - - 1 1 160 150 0 1 150 e« Secretaries,Reception 2 2 165 550 4 4 400 1,350 100 0 4 400 1,350 2* Grants and Contracts Management Office a* G & C Mgmt. Officer 1 1 260 1 1 220 220 0 1 220 b. G & C Mgmt. Specialist 1 1 130 1 1 200 200 0 1 200 o. Budget & Reports Analyst - - - 1 1 100 100 0 1 100 d. Committee Mgmt.Officer 1 1 120 1 1 100 100 0 1 100 e. Admin. Assistant 1 1 50 1 1 100 100 0 1 100 f. Clerks, typist. Messenger 2 2 100 4 4 320 70 90 0 4 320 g. Office Machine Operate! ► - - - 1 1 70 70 0 1 70 h. Secretaries 2 1 210 870 1 2 200 1,310 100 0 2 200 1,310 3. Institutional Support Management Program a« Grants Mgmt.Specialist 1 1 140 2 2 300 150 0 2 300 b. Grants Mgmt. assistant 1 1 120 1 1 100 100 0 1 100 c. Secretaries 1 1 100 1 1 70 70 0 1 70 d. Clerk -typist - - - 360 1 1 70 540 70 0 1 70 540 4. Communications Projects Management a. Grants Mgmt.Specialist 1 1 190 2 2 300 150 0 - 2 300 b. Secretary 1 - 100 290 1 1 70 370 70 0 1 70 370 Room 1 Sta 969 P Area Subtotal Sta 19 7 P 4 Area Subtotal GSA HEV7 Guide 0 T L C Sp S MAI P CN BLDC Area }. 1974 Subtotal LEI P JCBC BI Area JDG. 1974 Subtob al REMARKS 5* Grants Processing a« Grants Process* Office r - - - 1 1 150 100 0 1 150 b. Grants Assistant 1 1 100 1 1 100 100 0 1 100 o* Grants Clerks 3 3 270 370 6 6 640 790 90 0 6 640 790 19 2,440 36 4,360 36 4,360 B. Publications and Translations Division 1* Immediate Office a* Division Chief 1 1 190 1 1 300 300 0 1 300 b. Grants and Contracts Coordinator - - - 1 1 100 100 0 1 100 c. Seoretary 2 1 190 380 1 1 100 500 100 0 1 100 600 2. International Programs Branch a* Branch Chief 1 1 200 200 0 1 200 b.Int'l. Comm. Off. 1 - 130 1 1 160 160 0 1 150 o. Translations Officer - - tm 1 1 160 150 0 1 150 d. Project Assistant - - 2 2 200 100 0 2 200 e. Seoretary, Clerk, Typist 1 120 260 4 4 280 980 70 0 4 280 980 3. Domestic Program Branch a. Branch Chief - - - 1 1 200 200 0 1 200 b. Domestic Publications Officer 1 1 130 2 2 300 160 0 2 300 c. Grants Assistant - - - 1 1 100 100 0 1 100 d. Secretary m 1 1 130 2 2 140 740 70 0 2 140 740 4 760 18 2,220 18 2,220 Room Sta 19 6 P 4 Area Subtotal Sta 1 9 P 7 4 Area Subtotal GSA HM Guide 0 T L c Sp S MAI P N BLDG Area . 1974 Subtotal LHNCi P 3C BID Area G. 1974 Subtot &1 REMARKS C. Research & Training Division !• Immediate Office a* Division Chief - - - 1 1 300 300 0 1 300 b. Grants and Contracts Coordinator - - - 1 1 100 100 0 1 100 c. Secretary 1 1 130 130 1 1 100 500 100 0 1 100 600 2. Training Grants Branch a* Branch Chief — - mm 1 1 200 200 b 1 200 b. Training Grants Officer 1 1 190 1 1 150 160 0 1 160 o. Grants assistant - - - 1 1 100 100 0 1 100 d. Secretary 1 - 130 320 2 2 140 690 70 0 2 140 590 3* Research & Develop. Branch a* Branch Chief mm mm - 1 1 200 200 0 1 200 b. Research & Development Grants Officer 1 1 160 1 1 150 150 0 1 150 o. Grants Assistant •* - 1 1 100 100 0 1 100 d. Secretary - - - 160 2 2 140 590 70 0 2 140 590 4.Special Projects Branch a. Branch Chief - - - 1 1 200 200 0 i 200 b. Special Projects Grants Officer - - 1 1 150 150 0 1 150 c. Grants Assistant - - - 1 1 100 100 0 1 100 d. Secretary - - - 0 2 2 140 590 70 0 2 140 590 L D. Facilities & Resources Divisit >n 3 eio 18 2,270 18 2,270 1. immediate Office a* Division Chief 1 1 260 1 1 500 300 0 1 300 b. Deputy Division Chief - - - 1 1 200 200 0 1 200 o. Secretaries 2 2 160 410 2 2 200 700 100 o 2 200 700 Room Sta 19 6 P 9 Area Subtotal Sta 1 P 3 7 4 Area Subtotal GSA HEW Guide 0 T L C |Sp s MAI P N BLDC Area rV 1974 Subtotal LHNC P JBC Bli Area )G. 1974 Subtotal REMARKS 2« Regional Medical Library Branch a« Branch Chief 1 1 130 1 1 200 200 0 1 200 b. Regional Grant Officer 1 1 130 1 1 150 150 0 1 150 o» Grants Assistant m - - 1 1 100 100 0 1 100 d« Secretaries 1 1 130 390 2 2 140 690 70 0 2 140 590 3* Medical Library Resources Branch a* Branch Chief mm 1 1 200 200 0 1 200 b. Resource Grants Officer 1 1 110 1 1 160 150 0 1 150 o* Grants Assistant 1 1 90 1 1 100 100 0 1 100 d. Secretary 2 2 2,10 410 2 2 140 590 70 0 2 140 590 4* Construction Grants Branch a* Construction Grants Off; .cer 1 1 130 1 1 200 200 0 1 200 b. Grants Assistant 1 - 90 1 1 100 100 0 1 100 o. Architect (DRPR-NIH) 1 1 120 1 1 200 200 0 1 200 d* Secretary 1 mm 110 450 1 1 70 570 70 0 1 70 670 E* Special Purpose Space 1. Conference Rooms « 12 470 1,660 18 1500 2,450 0 18 1500 2,460 2. Central Files - - 156 - - 370 0 370 3. Duplication, Collating Supply - - 313 940 - - - 1,870 0 0 - 1,870 TOTALS * IV - BMP 38 6,410 90 13,170 90 13,170 Room 1 Sta 9 6 9 P Area Subtotal Sta 1 P 9 7 4 Area Subtotal GSA HEW Guide 0 T L C Sp S main p BLDG. Area 1974 Subtotal LHNCBC BLD P | Area 0. 1974 Subtotal REMARKS V* Specialized Information Services A* Office of Associate Director !• Associate director M133 1 1 190 1 1 300 300 0 1 300 2. Deputy Associate Director 3* Staff Assistant 4. Administrative Office 5. Clerical Support M132 M132 2 2 1 1 230 230 1 1 9 8 1 1 9 8 300 150 1160 650 500 100 150 90 200 70 100 0 0 0 0 1 1 9 8 300 160 1160 660 3 650 20 2, £>60 20 2,£>60 B. Toxicology Infomation Exchange Staff !• Immediate Office a* Head, TIE 1 1 300 300 0 1 300 b. Deputy Head, TIE o* Clerical Support 1 4 1 4 200 340 840 200 70 100 0 0 1 4 200 340 840 2* Referral Operations a* Chief, RO 1 1 200 200 0 1 200 b. Deputy Chief, RO c. Referral Specialist 1 3 1 3 200 500 200 150 200 0 0 1 3 200 500 d. Referral assistants e. Clerical Support 5 4 5 4 500 340 1,740 100 70 100 0 0 5 4 500 340 1,740 3, Source Information a* Chief, S.I. A54 1 1 180 1 1 200 200 0 1 200 b. Deputy Chief, S.I. 1 1 200 200 0 1 200 c. Source Specialist d. Source Analyst e. Clerical Support 180 4 5 5 4 5 5 600 550 510 2,060 150 100 150 70 100 0 0 0 4 5 5 600 650 510 2,060 Room Sta 19 6 P 9 Area Subtot al Sta 1 9 P 7 4 Area Subtotal GSA HEWT Guide 0 T L c Sp s MAB P r BLDG, Area 1974 Subtotal LHNCI P *C BLD< Area 1. 1974 Subtotal REMARKS 4, Terminology Development a* Chief, TD 1 1 200 200 0 1 200 b. Deputy Chief, TD o. Terminology Specialists d. Terminology Assistants e« Clerical Support 1 9 5 8 1 9 5 8 200 1400 600 650 200 150 200 100 150 70 90 0 0 0 0 1 9 5 8 200 1400 600 650 1 180 60 7,690 60 7,690 C. Services Development Staff 1« Immediate Office a* Head, SDS 1 1 300 300 0 1 300 b, Deputy Head, SDS o, Clerical 1 4 1 4 200 340 840 200 70 100 0 0 1 4 200 340 840 2* File Organization a* Chief, FO 154 e 1 1 220 1 1 200 200 0 1 200 b, Deputy Chief, FO 1 1 200 200 0 1 200 o* Analysts 2 2 300 160 0 2 300 d« Statistician 1 1 100 100 0 1 100 e* Specialist f* Clerical Support 5* Systems Design a* Chief, SD 154d A64 2 1 2 1 170 100 490 1 4 1 1 4 1 100 340 200 1,240 100 70 100 200 0 0 0 1 4 1 100 340 200 1,240 b. Deputy Chief, SD 1 1 200 200 0 1 200 o. System Analyst 2 2 300 160 0 2 300 d, System Programmers 2 2 300 160 0 2 300 e« Communication Engineers 1 1 100 100 0 1 100 f* Computer Engineer 1 1 100 100 0 1 100 g« Capability Coordinator h. Clerical Support 1 5 1 5 100 410 1,710 100 70 100 0 0 1 5 100 410 1,710 Room St a i 9 e p 9 Area Subtotal Sta 1 9 p 7 4 Area Subtotal GSA HEW Guide 0 T L C SP s ma: p [11 BLD Area G. 1974 Subtotal • LHNC P IBC BIJ Area DG. 1974 Subtotal REMaRKS 4* Products & Services a* Chief, P & S A54a 1 i 170 1 1 200 200 0 1 200 b. Deputy Chief, P & S o* Product Planner A54b 2 2 220 1 2 1 2 200 350 200 160 200 100 0 0 1 2 200 360 d* Product Analyst A54 1 1 70 5 5 700 160 0 5 700 e« Product Assist ant f* Clerical Support A54 1 1 100 560 3 5 3 5 300 410 2,160 100 70 100 0 0 3 5 300 410 2,160 9 1,050 47 1 47 5,9fe0 D. Drug Literature Program 1# Head, DLt> A54c 1 1 140 1 1 200 200 0 1 200 2* Deputy Head, DLP - 1 1 200 200 0 1 200 3. Administrative Assistant 1 1 160 150 0 1 150 4* DLP Specialists A54 4 4 290 5 5 750 160 0 5 760 5* DLP Assistants 6. Clerical Support ) 2 C 100 100 6 5 6 5 600 410 100 70 100 0 0 - 6 5 600 410 - 7 630 19 2,310 19 2,310 E* Common Space !• Storage s 2* Communications Room 600 T 600 3* Conference Room w/AV Facilities C 4* Staff Reading Room (Special Library) 1200 0 1200 5* File & Miscellaneous 580 0 0 580 0 1,800 1,800 F. Other Personnel 1* Trainees 1 70 7 t 0 2* Contract Personnel 1 70 1 t 0 140 TOTAL - V - SIS 20 3,230 146 20,310 146 20,310 Room St a L 9 6 P 3 Area Subtotal St a 1 9 P 7 4 Area Subtotal GSA HBW Guide 0 T L C Sp P MAI P N BLDG Area r. 1974 Subtotal LHNC P BC BU Area >G. 1974 Subtotal REMARKS VI. LISTER HILL NATIONAL CENTER FOR BIOMEDICAL COMMUNICATIONS A* Office of the Director - LHNCBC 1. Director M140 1 1 320 1 1 360 - 0 1 360 2* Deputy Director M139 1 1 250 1 1 300 - 0 1 300 3. Special Ass’ts to Director M135 1 1 180 2 2 400 200 0 2 400 4. Administrative Officer 5. Secretaries M124 2 2 240 1 5 1 5 150 490 150 90 100 0 0 1 5 160 490 6. Reception Area 200 0 200 7. Receptionist 1 90 90 0 1 90 8. Visitors* Study 1 - 300 0 300 9. Conference Room 450 C 450 10. Management Analysis Facility 450 0 450 5 990 11 3,190 11 3,190 B. Plans and Management Branch TT Chief 1 1 300 300 0 1 300 2* Professionals C19 1 200 1 io 10 1500 150 0 10 1500 3* Technical i 2 2 200 100 0 2 200 4. Secretaries C21 1 1 100 4 4 370 70 0 4 370 2 300 17 2,370 17 2,370 C. Research and Development 1. Chief M137 1 180 1 1 300 300 0 1 300 2* Professionals 8 8 1200 160 0 8 1200 3* Technical Specialists 4. Secretaries M132 2 1 230 4 4 4 4 600 310 100 70 100 0 0 4 4 600 310 5. Contractors 10 1000 0 1000 Room St a 19 6 P 9 Urea Subtotal St a 1 P 9 7 4 Area Subtotal GSA HEW Guide 0 T L C Sp S MA] p H BLDC Area r. 1974 Subtotal LHNC P JBC B LI Area )G. 1974 Subtotal Remarks 6# Laboratories a* Specialized Education Equipment Applications 600 T 600 b. Computers & Peripheral Devices 1000 T 1000 o. Electronic 600 T 600 d* Communications 600 T 600 e. Equipment Storage 400 s 400 f. Test Equipment Maintenaice 300 T 300 g. Material Storage 250 s 250 h. Technical Coni'./Workshop Areas - 2 ® 250 s.f. 500 T C 500 2 410 7,660 17 7,660 Network Engineering,Communication 3 and Operations Branch 1. Chief C17 1 1 200 1 1 300 300 0 1 300 2. Professionals M132 1 1 130 12 12 1800 150 0 12 1800 3. Technical 4* Secretaries C18 1 1 170 15 7 15 7 1500 610 100 70 100 0 0 15 7 1500 610 5* Contractors 25 0 2500 0 0 2500 6, Admin. Areas 200 200 7. Remote Information Systems Center. a# Communications Network Mgmt. Monitoring, Schedules Media Selection, Program Execution, Quality and Product Control > 1000 T 1000 b» Remote Control Equip. Facil 148 100 1700 T 1700 o. Public Viewing and Orientation Area 300 < 0 300 8. Data Processing and Data Transmission Central a« Technical Control Facility b. Network Systems Comm* Equipment Area c. Screening Room d. Specialized Education/ Information Broadcast Facility e. Network Programs Assembly Area f• Data Programs Files g. Audio and Audiovisual Programs Files h. Maintenance Area Room 1 St a 9 6 S P Area Subtotal St a 19 7 P 4 Area 1000 5000 550 1100 1250 200 300 1000 Subtotal GSA HEW Guide 0 T T T T T T T T T L C Sp S mah p * BLDG< Area 1974 Subtotal LHNCi P iC BLD( Area 1000 5000 560 1100 1250 200 300 1000 J, 1974 Subtotal REMARKS 3 700 35 20,310 35 20,310 E. Customer Products and Services Development Branch T7 Chief M138 1 1 190 1 1 300 300 0 1 300 2m Professionals M132 1 1 130 14 14 2100 160 0 14 2100 3« Secretaries M132 1 1 130 0 4 400 100 0 4 400 70 4. Reception Area & Receptionist 1 220 150 0 1 220 5. Contractors 15 0 1500 C 0 1500 nr 460 20 4,520 20 4,520 F, Reference Facility 2500 2600 0 0 0 2,500 0 2,500 G. Antenna Facility 1. TV Satellite Trans/Reoeive Antennas 36* T 36 2. Microwave Antenna Structure 16* T 16 3. Antenna Gear 2000 T 2000 2,050 2,050 TOTAL - VI. LHNCBC 15 2,840 100 42,600 100 42,600 TOTaL I - through VI 391 182,210 859 325,470 348 173,780 511 149,330 APPENDIX II 1974 MAC PROGRAM NIM NEEDS IN ATLANTA Pages II-l to II-6 APPENDIX II 1 9 6 9 1 9 7 4 NMAC PROGRAM - ATLANTA A. OFFICE OF THE DIRECTOR Room Sta P Area Subtotal Sta P Area Subtota !• Immediate Office of the Director &• Director’s Office B-13 1 1 360 1 1 360 b* Director’s Secretary B-15 1 1 150s 1 1 250s o# Asst, to Director’s Secretary B-15B 1 1 160 1 1 160 d* Deputy Director B-15A 1 1 300 1 1 360 e* Deputy Director’s Secretary B-15 1 1 150s 1 1 250s f. Asst. Director for Operations B-63 1 1 190 1 1 310 g. Secretary to Assistant Director for Operation* i B-55 1 1 80 1 1 80 h. Management Analyst B-6 V V 80 1 1 220 i. Associate in Biomedical Communication B-45 1 1 100 1 1 150 j. Special Asst•(Inquiry and Correspondence; B-46 1 1 140s 1 1 120 k. Asst, to Ij (Mail Control) B-46 1 1 1 1 200 1* Large Conference Hoorn B-19 440 440 m. Projection for Large Conference Room B-27 70 160 n. Small Conference Room 2220 300 3360 2« Administrative Staff Services a. Administrative Officer B-16 L 1 1 140 1 1 160 b* Secretary to Adminis- trative Officer B-16 1 i) 1 1 ) c. Fiscal Accounting -a-sst. B-16 1 i) 440s 1 X ) 680s d. Purchasing Agent B-16 1 i) 1 1) e« Fiscal Accounting Clerk B-16 1 1 ) 2 2 ) 1 9 6 9 1 £ 7 4 2* Administrative Staff Services (continued) Room St a P Area Subtotal Sta P Area Subtotal f• Projection Equipment Operator 108M 1 1 1 1 g* Supply Clerk SSB-S1/ ’ 1 1 580 1 1 840 3* Special Staff Services a. Special Projects Officer 1 1 (*) 1 1 200 b. Information and Publications Officer B-40 1 1 150 1 1 190 c. I & P Office B-44 2 2 120s 3 3 200 d. AV Reference Room 108K V V 140 1 440 e* Orientation & Visitors 390 200 1230 4* Storage and Miscellaneous a* General Supplies and Storage SSB-37 1055 ) b. Reprography and Thermofax Supplies B-ll 170 ) c* Printed Materials and Records B-31B ) d. For AV Reference Room 108 J 190 ) e* Reprography Room B-31A 21 60 1475 24 ) 6035 Total for Office of the Director 4,666 11,465 (*) Space occupied in Grady Memorial Hospital (CMTS) approximately 200 sq* ft* APPENDIX II NMAC PROGRAM - ATLANTA Room Sta 1 9 P 6 9 Area Subtotal Sta 1 £ P ) 7 4 Area Subtotal B. ACQUISITION, DISTRIBUTION, AND REFERENCE BRANCH (Chamblee Annex) 1. Office of Chief a* Chief and Conference Room 106A 1 1 200 1 1 200 b. Assistant Chief (Acquisition Program) 2 2 200 c« Senior Pictorial Re- viewer & Researcher 112 1 1 65s 0 d* Secretary to Chief 106 1 1 110 1 1 110 e. Clerk-Typist 112 1 1 65s 440 2 2 130 640 2• Depository Section &• Office of Chief & Clerk Stenographer 155 2 2 110 2 2 200 b# AV Inspector & Reclaimer Work Area 146 1 1 940 2 2 375 c* Pictorial Reviewers & Researchers (Stills Stock and Archives) 119 2 2 1050 5 5 300 d* Archival and Stock Footage Storage 2000 e* Archival and Stock Projection Review(2) 270 750 f* Still Picture Storage 2000 g. Support Materials Storage 200 h* Reference Area - Archives/Stook 140 2510 400 6225 19 6 9 1 9 7 4 3* Distribution Section Room Sta P Area Subtotal Sta P Area Subtotal &• Office of Chief 145A 1 1 120 1 1 200 b* Secretary to Chief 143 1 1 120 1 1 120 o* Office - Film Librarian 143 1 1 100 1 1 100 d. Booking 131 6 5 360 6 6 1600 e* Film Distribution Center 145 9 9 2190 11 11 5000 f« Support Materials Storage 146B 190 400 g* Receiving 400 h. Inspection - Table 400 i« Inspection - Machine 250 j« Inspection - Projection 260 k. Shipping 3080 500 9120 4* Reference Section a* Office of Chief 126 1 i) 460s 1 1 200 b. Reference Librarian 126 1 i) 1 1 o. Editorial Clerk 126 1 i) 1 1 d. Clerk Typist 126 1 1 340 1 1 e* Support Materials Storage 100 200 f. Indexing & Compilation 1 1 1180 g, ADP - Cataloging 900 2 2 560 2140 5* General Storage 200 200 Total for Acquisition, Distribution, and Reference Branch 30 7,130 18,126 APPENDIX II 19 6 9 1 9 7 4 MAC PROGRAM - ATLANTA ROOM Sta P Area Subtotal Sta P Area Subtotal C. EDUCATIONAL SYSTEMS AND DEVELOPMENT BRANCH 1. Office of the Chief a* Chief B-43A V 1 1 200 b* Assistant Chief 1 1 150 o* Secretary to Chief B-43 V 1 1 230 580 2. Audiovisual Systems Planning Section &• Office of Chief B-43B 1 1 120 1 1 200 b. Secretary to Chief B-43 1 1 230s 1 1 130 c* Asst* Section Chief 1 1 120 1 1 150 d* Writer 1 1 130 e* Systems Specialist B-43C 2 2 280 f* Chief, Facilities Design B-43A 1 1 120s 1 1 150 g* Clerical 2 2 200 h* Systems Specialists 2 2 260 i* Facilities Design Specialists 1 1 200 j. Graphics (Drafting, Illustration ,Uodels) 4 400 k* Conference Rooms (2) 10 400 1* Storage 760 m* Equipment Display and Demonstration 590 4 750 4000 19 6 9 1 9 7 4 3* Educational Studies and Development Section ROOM Sta P Area Subtotal Sta P Area Subtotal a* Office of Chief B-51 1 1 190 1 1 200 b* Asst* Section Chief B-49A 1 1 120 1 1 150 c* Secretary to Chief B-49 V 75s 1 1 175 d* Clerk Typist B-49 V 150 2 2 155 e* Educational Studies & Advisory Services (l) Activity Chief 1 1 120 f* Research & Evaluation (l) Activity Chief B-49C 1 1 120 1 1 160 (2) Educational Research Specialist B-47 1 1 55s 2 2 240 g, Educational Materials and Development (1) Activity Chief B-49B 1 1 120 1 1 150 (2) Writer #1 1 1 120 (3) Writer #2 1 1 120 (4) Editorial Clerk- Typist 1 1 120 h. Training (1) Activity Chief 1 1 150 (2) Educational Specialis Instructor b 2 2 240 i. Classroom Instruction & Support Space (l) Classroom #1 1800 (2) Classroom #2 500 (3) Classroom #3 500 (4) Study Carrell (16 @ 26 sq. ft*) 400 APPENDIX II 1 9 6 9 1 9 7 4 MAC PROGRAM - ATLANTA Room Sta P Area Subtotal Sta P Area Subtotal 3* Educational Studies and Development Section (continued) (5) Group Study Areas (6 @ 200 sq. ft.) 1000 (6) Conference Room #1 450 (7) Conference Room #2 450 (8) Photographic Arts Lai 500 (9) Graphic Arts Lab 600 (10) Instructional Resources Center 1000 (11) TV and Film Studio 600 J. Auditorium (shared) 830 4500 14,390 Total for Educational Systems and Development Branch 9 1,420 31 18,970 D. PRODUCTION BRANCH 1. Office of the Chief a* Chief 114A 1 1 140 1 1 140 b. Assistant Chief 116 1 1 140 1 1 140 o. Secretary to Chief 114 1 1 140 1 1 140 d. Asst. Chief for Television 144 1 1 140 1 1 140 e. Clerk Typists 142 2 2 110s 2 2 110s f. Branch Conference Rm. 140 140 200 g. Contracts Project Officer 2 2 220 h. Supply & Procurement Assistant 1 1 100 i. Projectionist 810 1 1 1,190 19 6 9 1 9 7 4 2* Preview Theaters Room Sta P Area Subtotal Sta P Area Subtotal a* Main Theater 145 740 740 b* New Theater 600 o* Projection Booths 147 2 160 2 160 d* Film Vault & Storage Area 108J 150 1,050 250 1,750 3* Writers & Directors Staff a* Chief Writer 108L 1 1 110 1 1 150 b, Staff Writer it1 108C 1 1 55s 1 1 140 c. Staff Writer #2 1 1 140 d. Staff Writer #3 1 1 140 e. Clerk Typist 1 1 110 f. Producer-Director jfl 108H 1 1 150 1 1 150 g, Producer-Director f/-2 108D 1 1 110 1 1 110 h* Producer-Director #3 108F 1 1 110 1 1 110 i* Producer-Director #4 108B 1 1 110 1 1 110 J# Producer-Director :,/5 10 8 A 1 1 110 1 1 110 k. Producer-Director tr6 108 C 1 1 55s 1 1 110 1. Producer-Director if7 1 1 110 m. Producer-Director fQ 1 1 110 n. Production Assistant 110 1 1 110 1 1 110 o» Open Conference/ Training Area 108 250 1,170 250 1,960 19 6 9 1 9 7 4 6* Film Editing and Laboratory Section (continued) Room St a P Area Subtotal Sta P Area Subtotal h* Film Printing Room #6 SB-22( 60 ) i* Sensitometrio Room, Raw Film Stock SB-22* r i 60 1 ) J. M*F* Processing-Dry- side SB-16 3 460 3 ) k* M.P* Processing - Wet - side SB-161 . 1 100s 1 ) 1* Supply, Chemical Mixing and Storage £ SB-12£ . 1 150 1 400 m. Laboratory Storage SB-16i 90s 300 n. Film Editors £ ►SB-33 4 4 810 7 7 1410 o* Film Editing (Negative Assembly) £ SB-36 1 1 180 2,610 1 1 180 5,290 7# Sound & Electronics Section a. Rerecord Theater (Area V) £ B-29B 730 1000 b* Isolation Booth £ B-29A B-31A 1 70 60s 1 100 60 c« Audio Recording & Playback (Area IV) £ B-27B 2 2 340 2 2 620 d* Sound Department Storage^ B-27D 320 750 e* Videotaping and TV Production Control (area I) IB-27C 3 3 720) 3 3 ) f• Area II £ 1B-27F 2 2 130) 2 2 ) 4000 g. Area III Balcony ►B-27G 630) ) h. Videotape Storage £ £ IB-19 1SB-18 200) 100) 500 i* Mobile TV Unit Storage 3,300 800 7,830 APPENDIX II 19 6 9 1 9 7 4 Nl.lh-C PROGRAM — ATLANTA Room St a P Area Subtotal St a P Area Subtota 4* Art and Animation Section a. Chief 117 i) 1 280 b. Animation Artists 117 2 2 ) 1280s 2 2 250 o. Artist-Illustrators 117 6 6 ) 6 6 750 d* Storage & ‘*ork Room 121 140 200 e. Storage & ProJ. Room 119 100 300 f, Oxberry Camera & Stand SSB2* i 1 200 1 200 g. M.P. Optical Printing Room SSB2: . 2 190 1,910 2 190 2,170 5* Camera Section a* Chief 5SB19 1 1 110 1 1 110 b. Office Area c* Office & Equipment Storage 5SB20 i) 3) 4 230 6 6 380 d. M.P. Film Loading Room SSB2C IA 20 40 e. Supply Room. Film Vault 5SB12 50s 300 f. Equipment Room ISB43 100 510 200 1,030 6. Film Editing and Laboratory Section a. Chief SB-21 . 1 1 100 1 i) b. Film Inspection and Timing SB-22 : 3 3 250 4 4 ) c. Film Printing Rm. fl SB-22 IB 2 2 60 2 2 ) d. Film Printing Rm. $2 SB-22 ;C 60 ) e. Film Printing Rm. #3 SB-22 D 110 ) f. Film Printing Rm. #4 SB-22 ;E 60 ) 3000 g. Film Printing Rm. #5 SB-22 :H 60 ) 1 9 6 9 1 9 7 4 9# Still Photographic Section (continued) Room Sta P Area Subtotal Sta P Area Subtotal (2) Darkroom - Photo- mic* Prints 2 B-15A! 1 80 1 80 (3) Photomic* Shooting and Storage £ j B-15AJ 2-3 1 130 2-3 1 130 i* Storage of Photo- Equipment (Hallway) £ £ B-10 B-10B 130 10 340 J# Studio-Storage S B-10A 400s 570 k. Slide Copying s B-10 30 60 1* Filmstrips and Slides from Art Work s B-10D 2-3 90 2-3 90 nu Dark Hoorn - B&W Prints s B-10H 1-2 170 1-2 170 n. Copy Large Work - Robertson Camera s s B-38A B-38B 1-2 280 1-2 280 0. B&W Printing s 3-10J 1 100 1 100 p# Chemical Mixing & Storage 3B-10G 1 30 1 30 q. Dark Room - B&W Prints 3B-10F 1 70 1 70 r* Wash & Dry - B&W Prints 3B-10E 2 60 2 60 s* Hot Press Work Room 127 1 1 270 3,200 1 1 270 4,220 Total for Production Branch 66 20,796 83 48,065 GRAND TOTAL 126 34,010 180 96,625 appendix ii 19 6 9 1 9 7 4 MAC PROGRAM - ATLANTA Roomi Sta P Area Subtotal Sta P Area Subtotal 8. Staging Section a# Make-up - Women's Dressing Room 5SB-30 n3 170 3 340 b.'Stage Set Fabrication Shop 5SB-2 3 540 4 ) 4 5600 o. Storage of Sets 5SB-3 ) d. Silent Stage 5SB-3 3 3 2280) 3 3 2280) e. Sound Stage #1 (TV) i JSB-2J 4 2280) 4 2280) f. Sound Stage #2 (MP) 5030 g. Sound Stage #3 (MP) 5030 h. Equipment Maintenance and Repair 1 5SB-7 3 400 4 1 1500 i. Equipment & Property Storage i isb-s*: 565 6,235 665 22,625 9* Still Photographic Section a. Chief £ 1B-19C 1 1 170 1 1 200 b. Project Supervisor (assistant) £ B-191 1 1 120 1 1 120 c. Chief (Adm-Photo Lab) SB-9 1 1 130 1 1 130 d. Photo & Slide Work Room SB-IB 3 3 290 3 3 300 e. Storage - Mounted Photos, etc. SB-15 F 150 300 f. Processing - MW and Color Negatives SB-1S SB-15 D E 3 3 200 3 3 480 g. Processing - Color Positives SB-15 3 1 1 140 1 1 140 h. Photomicrography Unit (l) Chief - also Shooting SB-15 d 1 1 150 1 1 300 Appendix III Information Furnished to Architects 1. Scope of Work for a Study to Combine the Requirements of the National Medical Audiovisual Center and the National Library of Medicine in One Building. Dated 20 November 1968 and amended 7 March 1969. 2. New Organization Chart of the Department of Health, Education, and Welfare, 1968. 3. Organization Chart of the National Library of Medicine dated 10 September 1968. 4. National Library of Medicine, Preliminary Program and Financial Plan 1970-1974, Dated 14 October 1968. 5. The Development of the National Biomedical Communications Network, 1968. 6. Request for Proposal on "An automated Graphic Image Storage, Retrieval and Print-out Device for National Library of Medicine", dated 12 August 1968, 7. NLM Organization, dated August 8, 1968, amended October 24, 1968 and November 4, 1968. 8. Handling of Toxicological Information, a Report of the Presidents Science Advisory Committee, dated June 1966. 9. Memorandum from E, A, Miller, T, Bagg and D. Campbell dated November 22, 1968 Re: Film Vault Capacity, 10. Memorandum from S, T, Water, Dated November 27, 1968 Re: Microfilming Programs and Graphic Image Storage and Retrieval System. 11. Letter from Ren F. Read, Assistant Director of Civil Defense, Office of Civil Defense, Department of the Army to Mr. Dale S. Thompson, Director of General Services Department of HEW dated November 7, 1968 Re: Fallout Protection. 12. Memorandum from the Director, LHNCBC dated December 12, 1968 Re: Location of LHNCBC Floor Space in NLM's Proposed New Facility, NATIONAL LIBRARY OF MEDICINE WITH PROPOSED LHNCBC BUILDING O'CONNOR & KILHAM ARCHITECTS 1969